- Table 1 to Subpart MMMM of Part 60—Model Rule—Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units

Comply with these increments of progress By these dates aIncrement 1—Submit final control plan(Dates to be specified in state plan) Increment 2—Final compliance(Dates to be specified in state plan) b

a Site-specific schedules can be used at the discretion of the state.

b The date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.