- § 381.501 - Applicability.
- § 381.505 - Certification of qualifying status as a small power production facility or cogeneration facility.
§ 381.501 - Applicability.
The fees set forth in this subpart apply to filings submitted on or after November 4, 1985.
§ 381.505 - Certification of qualifying status as a small power production facility or cogeneration facility.
(a) Unless the Commission orders direct billing under § 381.107 of this chapter or otherwise, the fee established for an application for Commission certification as a qualifying small power production facility, as defined in section 3(17) of the Federal Power Act, is $35,170 and the fee established for an application for Commission certification as a qualifying cogeneration facility, as defined in section 3(18) of the Federal Power Act, is $39,810.
(b) The fee filed under this section must be submitted in accordance with subpart A of this part and § 292.207(b)(2) of this chapter.