Collapse to view only § 725.8 - Report, plan and recommendation development and review.

§ 725.5 - Council studies.

All studies and appraisals performed by the Council pursuant to section 102 of Pub. L. 89-80 and any recommendations based on these activities shall include specific analyses for reflection of and opportunities to meet the objectives of E.O. 11988 and E.O. 11990. The Council's Floodplain Management Guidelines (43 FR 6030), E.O. 11988 and E.O. 11990 provide the basic evaluation tools for these analyses.

§ 725.6 - Principles, standards and procedures.

The Principles, Standards and Procedures established by the Council pursuant to section 103 of Pub. L. 89-80 shall reflect the provisions of the Executive Orders. These Principles, Standards and Procedures are found in 18 CFR parts 710 through 717.

§ 725.7 - Regional or river basin planning.

(a) In agreements between river basin commissions or other regional planning sponsors and the Council for the preparation and revision of regional and river basin Level B Studies and regional water resource management plans, the responsible official representing the river basin commission or regional planning sponsor shall certify to the Council that the following criteria have been or will be utilized as part of the planning process:

(1) Determination of whether proposed activities would be located in floodplains or wetlands, or, even if located outside of them, would have the potential to affect floodplains or wetlands;

(2) Avoidance of performing activities within floodplains or wetlands wherever there is a practicable alternative;

(3) Where avoidance of floodplains cannot be achieved, minimization of adverse impacts and support of floodplain development, and preservation and restoration of natural and beneficial floodplain values;

(4) Where avoidance of wetlands cannot be achieved, minimization of adverse impacts and support of new construction in wetlands, and preservation and enhancement of natural and beneficial wetlands values; and

(5) Involvement of the public in the floodplain management and wetlands protection decisionmaking process.

(b) The Council's Floodplain Management Guidelines (43 FR 6030) shall be used as the basis for implementing the criteria in § 725.7(a)(1) through (5).

(c) The responsible official representing the regional planning sponsor shall, to the fullest extent of his or her authority, ensure that any activities carried out under his or her plans and programs meet the criteria in § 725.7(a)(1) through (5).

§ 725.8 - Report, plan and recommendation development and review.

All reports, plans and recommendations received under section 104 of Pub. L. 89-80 shall be reviewed by the Council for reflection of and opportunities to meet the objectives of E.O. 11988 and 11990. This review shall be based on the criteria in § 725.7(a)(1) through (5), on E.O. 11988 and 11990, and on the Council's Floodplain Management Guidelines (43 FR 6030).

§ 725.9 - Reviews of compliance.

Reviews of compliance performed pursuant to section 304 of Pub. L. 89-80 shall include analysis of each program's treatment of floodplain management and wetland protection in accordance with the manner in which these concepts are expressed in E.O. 11988, 11990, and the Council's Floodplain Management Guidelines (43 FR 6030).