The 1964 amendments (Pub. L. 88-349) to the Davis-Bacon Act require, among other things, that the prevailing wage determined for Federal and federally assisted construction include the basic hourly rate of pay and the amount contributed by the contractor or subcontractor for certain fringe benefits (or the cost to them of such benefits). The purpose of this subpart is to explain the provisions of these amendments and make available in one place official interpretations of the fringe benefits provisions of the Davis-Bacon Act. These interpretations will guide the Department of Labor in carrying out its responsibilities under these provisions. These interpretations are intended also to provide guidance to contractors and their associations; laborers and mechanics and their organizations; and local, State, and Federal agencies. The interpretations contained in this subpart are authoritative and may be relied upon as provided for in section 10 of the Portal-to-Portal Act of 1947 (29 U.S.C. 259). The omission to discuss a particular problem in this subpart or in interpretations supplementing it should not be taken to indicate the adoption of any position by the Secretary of Labor with respect to such problem or to constitute an administrative interpretation, practice, or enforcement policy. Questions on matters not fully covered by this subpart may be referred to the Secretary for interpretation as provided in § 5.13.

[88 FR 57743, Aug. 23, 2023]

§ 5.21 - [Reserved]

§ 5.22 - Effect of the Davis-Bacon fringe benefits provisions.

The Davis-Bacon Act and the prevailing wage provisions of the statutes referenced in § 1.1 of this subtitle confer upon the Secretary of Labor the authority to predetermine, as minimum wages, those wage rates found to be prevailing for corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the area in which the work is to be performed. See the definitions of the terms “prevailing wage” and “area” in § 1.2 of this subtitle. The fringe benefits amendments enlarge the scope of this authority by including certain bona fide fringe benefits within the meaning of the terms “wages”, “scale of wages”, “wage rates”, “minimum wages”, and “prevailing wages”, as used in the Davis-Bacon Act.

[88 FR 57744, Aug. 23, 2023]

§ 5.23 - The statutory provisions.

Pursuant to the Davis-Bacon Act, as amended and codified at 40 U.S.C. 3141(2), the term “prevailing wages” and similar terms include the basic hourly rate of pay and, for the listed fringe benefits and other bona fide fringe benefits not required by other law, the contributions irrevocably made by a contractor or subcontractor to a trustee or third party pursuant to a bona fide fringe benefit fund, plan, or program, and the costs to the contractor or subcontractor that may be reasonably anticipated in providing bona fide fringe benefits pursuant to an enforceable commitment to carry out a financially responsible plan or program, which was communicated in writing to the affected laborers and mechanics. Section 5.29 discusses specific fringe benefits that may be considered to be bona fide.

[88 FR 57744, Aug. 23, 2023]

§ 5.24 - The basic hourly rate of pay.

“The basic hourly rate of pay” is that part of a laborer's or mechanic's wages which the Secretary of Labor would have found and included in wage determinations prior to the 1964 amendments. The Secretary of Labor is required to continue to make a separate finding of this portion of the wage. In general, this portion of the wage is the cash payment made directly to the laborer or mechanic. It does not include fringe benefits.

§ 5.25 - Rate of contribution or cost for fringe benefits.

(a) Under the amendments, the Secretary is obligated to make a separate finding of the rate of contribution or cost of fringe benefits. Only the amount of contributions or costs for fringe benefits which meet the requirements of the act will be considered by the Secretary. These requirements are discussed in this subpart.

(b) The rate of contribution or cost is ordinarily an hourly rate, and will be reflected in the wage determination as such. In some cases, however, the contribution or cost for certain fringe benefits may be expressed in a formula or method of payment other than an hourly rate. In such cases, the Secretary may in his discretion express in the wage determination the rate of contribution or cost used in the formula or method or may convert it to an hourly rate of pay whenever he finds that such action would facilitate the administration of the Act. See § 5.5(a)(1)(i) and (iii).

(c) Except as provided in this section, contractors must “annualize” all contributions to fringe benefit plans (or the reasonably anticipated costs of an unfunded benefit plan) to determine the hourly equivalent for which they may take credit against their fringe benefit obligation. The “annualization” principle reflects that DBRA credit for contributions made to bona fide fringe benefit plans (or the reasonably anticipated costs of an unfunded benefit plan) is allowed based on the effective rate of contributions or costs incurred for total hours worked during the year (or a shorter time period) by a laborer or mechanic.

(1) Method of computation. To annualize the cost of providing a fringe benefit, a contractor must divide the total cost of the fringe benefit contribution (or the reasonably anticipated costs of an unfunded benefit plan) by the total number of hours worked on both private (non-DBRA) work and work covered by the Davis-Bacon Act and/or Davis-Bacon Related Acts (DBRA-covered work) during the time period to which the cost is attributable to determine the rate of contribution per hour. If the amount of contribution varies per worker, credit must be determined separately for the amount contributed on behalf of each worker.

(2) Exception requests. Contractors, plans, and other interested parties may request an exception from the annualization requirement by submitting a request to the WHD Administrator. A request for an exception may be granted only if each of the requirements of paragraph (c)(3) of this section is satisfied. Contributions to defined contribution pension plans (DCPPs) are excepted from the annualization requirement, and exception requests therefore are not required in connection with DCPPs, provided that each of the requirements of paragraph (c)(3) is satisfied and the DCPP provides for immediate participation and essentially immediate vesting (i.e., the benefit vests within the first 500 hours worked). Requests must be submitted in writing to the Division of Government Contracts Enforcement by email to [email protected] or by mail to Director, Division of Government Contracts Enforcement, Wage and Hour Division, U.S. Department of Labor, 200 Constitution Ave. NW, Room S-3502, Washington, DC 20210.

(3) Exception requirements. Contributions to a bona fide fringe benefit plan (or the reasonably anticipated costs of an unfunded benefit plan) are excepted from the annualization requirement if all of the following criteria are satisfied:

(i) The benefit provided is not continuous in nature. A benefit is not continuous in nature when it is not available to a participant without penalty throughout the year or other time period to which the cost of the benefit is attributable; and

(ii) The benefit does not compensate both private work and DBRA-covered work. A benefit does not compensate both private and DBRA-covered work if any benefits attributable to periods of private work are wholly paid for by compensation for private work.

[29 FR 13465, Sept. 30, 1964, as amended at 88 FR 57744, Aug. 23, 2023]

§ 5.26 - “* * * contribution irrevocably made * * * to a trustee or to a third person”.

(a) Requirements. The following requirements apply to any fringe benefit contributions made to a trustee or to a third person pursuant to a fund, plan, or program:

(1) Such contributions must be made irrevocably;

(2) The trustee or third person may not be affiliated with the contractor or subcontractor;

(3) A trustee must adhere to any fiduciary responsibilities applicable under law; and

(4) The trust or fund must not permit the contractor or subcontractor to recapture any of the contributions paid in or any way divert the funds to its own use or benefit.

(b) Excess payments. Notwithstanding the above, a contractor or subcontractor may recover sums which it had paid to a trustee or third person in excess of the contributions actually called for by the plan, such as excess payments made in error or in order to cover the estimated cost of contributions at a time when the exact amount of the necessary contributions is not yet known. For example, a benefit plan may provide for definite insurance benefits for employees in the event of contingencies such as death, sickness, or accident, with the cost of such definite benefits borne by the contractor or subcontractor. In such a case, if the insurance company returns the amount that the contractor or subcontractor paid in excess of the amount required to provide the benefits, this will not be deemed a recapture or diversion by the employer of contributions made pursuant to the plan. (See Report of the Senate Committee on Labor and Public Welfare, S. Rep. No. 963, 88th Cong., 2d Sess., p. 5.)

[88 FR 57744, Aug. 23, 2023]

§ 5.27 - “* * * fund, plan, or program”.

The contributions for fringe benefits must be made pursuant to a fund, plan or program (sec. 1(b)(2)(A) of the act). The phrase “fund, plan, or program” is merely intended to recognize the various types of arrangements commonly used to provide fringe benefits through employer contributions. The phrase is identical with language contained in section 3(1) of the Welfare and Pension Plans Disclosure Act. In interpreting this phrase, the Secretary will be guided by the experience of the Department in administering the latter statute. (See Report of Senate Committee on Labor and Public Welfare, S. Rep. No. 963, 88th Cong., 2d Sess., p. 5.)

§ 5.28 - Unfunded plans.

(a) The costs to a contractor or subcontractor which may be reasonably anticipated in providing benefits of the types described in the Act, pursuant to an enforceable commitment to carry out a financially responsible plan or program, are considered fringe benefits within the meaning of the Act (see 40 U.S.C. 3141(2)(B)(ii)). The legislative history suggests that these provisions were intended to permit the consideration of fringe benefits meeting these requirements, among others, and which are provided from the general assets of a contractor or subcontractor. (Report of the House Committee on Education and Labor, H. Rep. No. 308, 88th Cong., 1st Sess., p. 4; see also S. Rep. No. 963, p. 6.)

(b) Such a benefit plan or program, commonly referred to as an unfunded plan, may not constitute a fringe benefit within the meaning of the Act unless:

(1) It could be reasonably anticipated to provide the benefits described in the Act;

(2) It represents a commitment that can be legally enforced;

(3) It is carried out under a financially responsible plan or program;

(4) The plan or program providing the benefits has been communicated in writing to the laborers and mechanics affected; and

(5) The contractor or subcontractor requests and receives approval of the plan or program from the Secretary, as described in paragraph (c) of this section.

(c) To receive approval of an unfunded plan or program, a contractor or subcontractor must demonstrate in its request to the Secretary that the unfunded plan or program, and the benefits provided under such plan or program, are “bona fide,” meet the requirements set forth in paragraphs (b)(1) through (4) of this section, and are otherwise consistent with the Act. The request must include sufficient documentation to enable the Secretary to evaluate these criteria. Contractors and subcontractors may request approval of an unfunded plan or program by submitting a written request in one of the following manners:

(1) By mail to the United States Department of Labor, Wage and Hour Division, Director, Division of Government Contracts Enforcement, 200 Constitution Ave. NW, Room S-3502, Washington, DC 20210;

(2) By email to [email protected] (or its successor email address); or

(3) By any other means directed by the Administrator.

(d) Unfunded plans or programs may not be used as a means of avoiding the Act's requirements. The words “reasonably anticipated” require that any unfunded plan or program be able to withstand a test of actuarial soundness. Moreover, as in the case of other fringe benefits payable under the Act, an unfunded plan or program must be “bona fide” and not a mere simulation or sham for avoiding compliance with the Act. To prevent these provisions from being used to avoid compliance with the Act, the Secretary may direct a contractor or subcontractor to set aside in an account assets which, under sound actuarial principles, will be sufficient to meet future obligations under the plan. Such an account must be preserved for the purpose intended. (S. Rep. No. 963, p. 6.)

[88 FR 57744, Aug. 23, 2023]

§ 5.29 - Specific fringe benefits.

(a) The act lists all types of fringe benefits which the Congress considered to be common in the construction industry as a whole. These include the following: Medical or hospital care, pensions on retirement or death, compensation for injuries or illness resulting from occupational activity, or insurance to provide any of the foregoing, unemployment benefits, life insurance, disability and sickness insurance, or accident insurance, vacation and holiday pay, defrayment of costs of apprenticeship or other similar programs, or other bona fide fringe benefits, but only where the contractor or subcontractor is not required by other Federal, State, or local law to provide any of such benefits.

(b) The legislative history indicates that it was not the intent of the Congress to impose specific standards relating to administration of fringe benefits. It was assumed that the majority of fringe benefits arrangements of this nature will be those which are administered in accordance with requirements of section 302(c)(5) of the National Labor Relations Act, as amended (S. Rep. No. 963, p. 5).

(c) The term “other bona fide fringe benefits” is the so-called “open end” provision. This was included so that new fringe benefits may be recognized by the Secretary as they become prevailing. It was pointed out that a particular fringe benefit need not be recognized beyond a particular area in order for the Secretary to find that it is prevailing in that area. (S. Rep. No. 963, p. 6).

(d) The legislative reports indicate that, to insure against considering and giving credit to any and all fringe benefits, some of which might be illusory or not genuine, the qualification was included that such fringe benefits must be “bona fide” (H. Rep. No. 308, p. 4; S. Rep. No. 963, p. 6). No difficulty is anticipated in determining whether a particular fringe benefit is “bona fide” in the ordinary case where the benefits are those common in the construction industry and which are established under a usual fund, plan, or program. This would be typically the case of those fringe benefits listed in paragraph (a) of this section which are funded under a trust or insurance program. Contractors may take credit for contributions made under such conventional plans without requesting the approval of the Secretary of Labor under § 5.5(a)(1)(iv).

(e) Where the plan is not of the conventional type described in paragraph (d) of this section, the Secretary must examine the facts and circumstances to determine whether fringe benefits under the plan are “bona fide” in accordance with requirements of the Act. This is particularly true with respect to unfunded plans discussed in § 5.28. Contractors or subcontractors seeking credit under the Act for costs incurred for such plans must request specific approval from the Secretary under § 5.5(a)(1)(iv).

(f) The act excludes fringe benefits which a contractor or subcontractor is obligated to provide under other Federal, State, or local law. No credit may be taken under the act for the payments made for such benefits. For example, payment for workmen's compensation insurance under either a compulsory or elective State statute are not considered payments for fringe benefits under the Act. While each situation must be separately considered on its own merits, payments made for travel, subsistence or to industry promotion funds are not normally payments for fringe benefits under the Act. The omission in the Act of any express reference to these payments, which are common in the construction industry, suggests that these payments should not normally be regarded as bona fide fringe benefits under the Act.

(g) For a contractor or subcontractor to take credit for the costs of an apprenticeship program, the following requirements must be met:

(1) The program, in addition to meeting all other relevant requirements for fringe benefits in this subpart, must be registered with the Department of Labor's Employment and Training Administration, Office of Apprenticeship (“OA”), or with a State Apprenticeship Agency recognized by the OA.

(2) The contractor or subcontractor may only take credit for amounts reasonably related to the costs of the apprenticeship benefits actually provided to the contractor's employees, such as instruction, books, and tools or materials. It may not take credit for voluntary contributions beyond such costs. Amounts the employer is required to contribute by a collective bargaining agreement or by a bona fide apprenticeship plan will be presumed to be reasonably related to such costs in the absence of evidence to the contrary.

(3) Costs incurred for the apprenticeship for one classification of laborer or mechanic may not be used to offset costs incurred for another classification.

(4) In applying the annualization principle to compute the allowable fringe benefit credit pursuant to § 5.25, the total number of working hours of employees to which the cost of an apprenticeship program is attributable is limited to the total number of hours worked by laborers and mechanics in the apprentice's classification. For example, if a contractor enrolls an employee in an apprenticeship program for carpenters, the permissible hourly Davis-Bacon credit is determined by dividing the cost of the program by the total number of hours worked by the contractor's carpenters and carpenters' apprentices on covered and non-covered projects during the time period to which the cost is attributable, and such credit may only be applied against the contractor's prevailing wage obligations for all carpenters and carpenters' apprentices for each hour worked on the covered project.

[29 FR 13465, Sept. 30, 1964, as amended at 88 FR 57745, Aug. 23, 2023]

§ 5.30 - Types of wage determinations.

(a) When fringe benefits are prevailing for various classes of laborers and mechanics in the area of proposed construction, such benefits are includable in any Davis-Bacon wage determination. The examples contained in paragraph (c) of this section demonstrate how fringe benefits may be listed on wage determinations in such cases.

(b) Wage determinations do not include fringe benefits for various classes of laborers and mechanics whenever such benefits do not prevail in the area of proposed construction. When this occurs, the wage determination will contain only the basic hourly rates of pay which are prevailing for the various classes of laborers and mechanics. An illustration of this situation is contained in paragraph (c) of this section.

(c) The following illustrates examples of the situations discussed in paragraph (a) and (b) of this section:

Figure 1 to Paragraph (c) [88 FR 57745, Aug. 23, 2023]

§ 5.31 - Meeting wage determination obligations.

(a) A contractor or subcontractor performing work subject to a Davis-Bacon wage determination may discharge their minimum wage obligations for the payment of both straight time wages and fringe benefits by paying in cash, making payments or incurring costs for “bona fide” fringe benefits of the types listed in the applicable wage determination or otherwise found prevailing by the Secretary of Labor, or by a combination thereof.

(b) A contractor or subcontractor may discharge their obligations for the payment of the basic hourly rates and the fringe benefits where both are contained in a wage determination applicable to their laborers or mechanics in the following ways:

(1) By paying not less than the basic hourly rate to the laborers or mechanics and by making contributions for “bona fide” fringe benefits in a total amount not less than the total of the fringe benefits required by the wage determination. For example, the obligations for “Laborer: common or general” in § 5.30, figure 1 to paragraph (c), will be met by the payment of a straight time hourly rate of not less than $21.93 and by contributions of not less than a total of $6.27 an hour for “bona fide” fringe benefits; or

(2) By paying in cash directly to laborers or mechanics for the basic hourly rate and by making an additional cash payment in lieu of the required benefits. For example, where an employer does not make payments or incur costs for fringe benefits, they would meet their obligations for “Laborer: common or general” in § 5.30, figure 1 to paragraph (c), by paying directly to the laborers a straight time hourly rate of not less than $28.60 ($21.93 basic hourly rate plus $6.27 for fringe benefits); or

(3) As stated in paragraph (a) of this section, the contractor or subcontractor may discharge their minimum wage obligations for the payment of straight time wages and fringe benefits by a combination of the methods illustrated in paragraphs (b)(1) and (2) of this section. Thus, for example, their obligations for “Laborer: common or general” may be met by an hourly rate, partly in cash and partly in payments or costs for fringe benefits which total not less than $28.60 ($21.93 basic hourly rate plus $6.27 for fringe benefits).

[88 FR 57746, Aug. 23, 2023]

§ 5.32 - Overtime payments.

(a) The act excludes amounts paid by a contractor or subcontractor for fringe benefits in the computation of overtime under the Fair Labor Standards Act, the Contract Work Hours and Safety Standards Act, and the Walsh-Healey Public Contracts Act whenever the overtime provisions of any of these statutes apply concurrently with the Davis-Bacon Act or its related prevailing wage statutes. It is clear from the legislative history that in no event can the regular or basic rate upon which premium pay for overtime is calculated under the aforementioned Federal statutes be less than the amount determined by the Secretary of Labor as the basic hourly rate (i.e. cash rate) under section 1(b)(1) of the Davis-Bacon Act. (See S. Rep. No. 963, p. 7.) Contributions by employees are not excluded from the regular or basic rate upon which overtime is computed under these statutes; that is, an employee's regular or basic straight-time rate is computed on his earnings before any deductions are made for the employee's contributions to fringe benefits. The contractor's contributions or costs for fringe benefits may be excluded in computing such rate so long as the exclusions do not reduce the regular or basic rate below the basic hourly rate contained in the wage determination.

(b) The legislative report notes that the phrase “contributions irrevocably made by a contractor or subcontractor to a trustee or to a third person pursuant to a fund, plan, or program” was added to the bill in Committee. This language in essence conforms to the overtime provisions of section 7(d)(4) of the Fair Labor Standards Act, as amended. The intent of the committee was to prevent any avoidance of overtime requirements under existing law. See H. Rep. No. 308, p. 5.

(c)(1) The act permits a contractor or subcontractor to pay a cash equivalent of any fringe benefits found prevailing by the Secretary of Labor. Such a cash equivalent would also be excludable in computing the regular or basic rate under the Federal overtime laws mentioned in paragraph (a). For example, the W construction contractor pays his laborers or mechanics $3.50 in cash under a wage determination of the Secretary of Labor which requires a basic hourly rate of $3 and a fringe benefit contribution of 50 cents. The contractor pays the 50 cents in cash because he made no payments and incurred no costs for fringe benefits. Overtime compensation in this case would be computed on a regular or basic rate of $3.00 an hour. However, in some cases a question of fact may be presented in ascertaining whether or not a cash payment made to laborers or mechanics is actually in lieu of a fringe benefit or is simply part of their straight time cash wage. In the latter situation, the cash payment is not excludable in computing overtime compensation. Consider the examples set forth in paragraphs (c)(2) and (3) of this section.

(2) The X construction contractor has for some time been paying $3.25 an hour to a mechanic as his basic cash wage plus 50 cents an hour as a contribution to a welfare and pension plan. The Secretary of Labor determines that a basic hourly rate of $3 an hour and a fringe benefit contribution of 50 cents are prevailing. The basic hourly rate or regular rate for overtime purposes would be $3.25, the rate actually paid as a basic cash wage for the employee of X, rather than the $3 rate determined as prevailing by the Secretary of Labor.

(3) Under the same prevailing wage determination, discussed in paragraph (c)(2) of this section, the Y construction contractor who has been paying $3 an hour as his basic cash wage on which he has been computing overtime compensation reduces the cash wage to $2.75 an hour but computes his costs of benefits under section 1(b)(2)(B) as $1 an hour. In this example the regular or basic hourly rate would continue to be $3 an hour. See S. Rep. No. 963, p. 7.

§ 5.33 - Administrative expenses of a contractor or subcontractor.

(a) Creditable costs. The costs incurred by a contractor's insurance carrier, third-party trust fund, or other third-party administrator that are directly related to the administration and delivery of bona fide fringe benefits to the contractor's laborers and mechanics can be credited towards the contractor's obligations under a Davis-Bacon wage determination. Thus, for example, a contractor may take credit for the premiums it pays to an insurance carrier or the contributions it makes to a third-party trust fund that both administers and delivers bona fide fringe benefits under a plan, where the insurance carrier or third-party trust fund uses those monies to pay for bona fide fringe benefits and for the administration and delivery of such benefits, including evaluating benefit claims, deciding whether they should be paid, approving referrals to specialists, and other reasonable costs of administering the plan. Similarly, a contractor may also take credit for monies paid to a third-party administrator to perform tasks that are directly related to the administration and delivery of bona fide fringe benefits, including under an unfunded plan.

(b) Noncreditable costs. A contractor's own administrative expenses incurred in connection with the provision of fringe benefits are considered business expenses of the firm and are therefore not creditable towards the contractor's prevailing wage obligations, including when the contractor pays a third party to perform such tasks in whole or in part. For example, a contractor may not take credit for the costs of office employees who perform tasks such as filling out medical insurance claim forms for submission to an insurance carrier, paying and tracking invoices from insurance carriers or plan administrators, updating the contractor's personnel records when workers are hired or separate from employment, sending lists of new hires and separations to insurance carriers or plan administrators, or sending out tax documents to the contractor's workers, nor can the contractor take credit for the cost of paying a third-party entity to perform these tasks. Additionally, recordkeeping costs associated with ensuring the contractor's compliance with the Davis-Bacon fringe benefit requirements, such as the cost of tracking the amount of a contractor's fringe benefit contributions or making sure contributions cover the fringe benefit amount claimed, are considered a contractor's own administrative expenses and are not considered directly related to the administration and delivery of bona fide fringe benefits. Thus, such costs are not creditable whether the contractor performs those tasks itself or whether it pays a third party a fee to perform those tasks.

(c) Questions regarding administrative expenses. Any questions regarding whether a particular cost or expense is creditable towards a contractor's prevailing wage obligations should be referred to the Administrator for resolution prior to any such credit being claimed.

[88 FR 57747, Aug. 23, 2023]