Collapse to view only § 254.55 - Spill response plans for facilities located in Alaska State waters seaward of the coast line in the Chukchi and Beaufort Seas.

§ 254.50 - Spill response plans for facilities located in State waters seaward of the coast line.

Owners or operators of facilities located in State waters seaward of the coast line must submit a spill-response plan to BSEE for approval. You may choose one of three methods to comply with this requirement. The three methods are described in §§ 254.51, 254.52, and 254.53.

§ 254.51 - Modifying an existing OCS OSRP.

You may modify an existing response plan covering a lease or facility on the OCS to include a lease or facility in State waters located seaward of the coast line. Since this OSRP would cover more than one lease or facility, it would be considered a Regional Response Plan. You should refer to § 254.3 and contact the appropriate regional BSEE office if you have any questions on how to prepare this Regional Response Plan.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36153, June 6, 2016]

§ 254.52 - Following the format for an OCS OSRP.

You may develop a response OSRP following the requirements for plans for OCS facilities found in subpart B of this part.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36153, June 6, 2016]

§ 254.53 - Submitting an OSRP developed under State requirements.

(a) You may submit a response plan to BSEE for approval that you developed in accordance with the laws or regulations of the appropriate State. The OSRP must contain all the elements the State and OPA require and must:

(1) Be consistent with the requirements of the National Contingency Plan and appropriate Area Contingency Plan(s).

(2) Identify a qualified individual and require immediate communication between that person and appropriate Federal officials and response personnel if there is a spill.

(3) Identify any private personnel and equipment necessary to remove, to the maximum extent practicable, a worst case discharge as defined in § 254.47. The plan must provide proof of contractual services or other evidence of a contractual agreement with any OSRO's or spill management team members who are not employees of the owner or operator.

(4) Describe the training, equipment testing, periodic unannounced drills, and response actions of personnel at the facility. These must ensure both the safety of the facility and the mitigation or prevention of a discharge or the substantial threat of a discharge.

(5) Describe the procedures you will use to periodically update and resubmit the plan for approval of each significant change.

(b) Your plan developed under State requirements also must include the following information:

(1) A list of the facilities and leases the plan covers and a map showing their location;

(2) A list of the types of oil handled, stored, or transported at the facility;

(3) Name and address of the State agency to whom the plan was submitted;

(4) Date you submitted the plan to the State;

(5) If the plan received formal approval, the name of the approving organization, the date of approval, and a copy of the State agency's approval letter if one was issued; and

(6) Identification of any regulations or standards used in preparing the plan.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36153, June 6, 2016]

§ 254.54 - Spill prevention for facilities located in State waters seaward of the coast line.

In addition to your OSRP, you must submit to the Chief, OSPD, a description of the steps you are taking to prevent spills of oil or mitigate a substantial threat of such a discharge. You must identify all State or Federal safety or pollution prevention requirements that apply to the prevention of oil spills from your facility, and demonstrate your compliance with these requirements. You also should include a description of industry safety and pollution prevention standards your facility meets. The Chief, OSPD may prescribe additional equipment or procedures for spill prevention if it is determined that your efforts to prevent spills do not reflect good industry practices.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36153, June 6, 2016]

§ 254.55 - Spill response plans for facilities located in Alaska State waters seaward of the coast line in the Chukchi and Beaufort Seas.

Response plans for facilities conducting exploratory drilling operations from a MODU seaward of the coast line in Alaska State waters in the Chukchi and Beaufort Seas must follow the requirements contained within subpart E of this part, in addition to the other requirements of this subpart. Such response plans must address how the source control procedures selected to comply with State law will be integrated into the planning, training, and exercise requirements of §§ 254.70(a), 254.90(a), and 254.90(c), in the event that the proposed operations do not incorporate the capping stack, cap and flow system, containment dome, and/or other similar subsea and surface devices and equipment and vessels referenced in those sections.