Collapse to view only § 39.62 - Space criteria for support facilities.
Grant Requirements and Procedures
- SECTION § 39.30 - General requirements for a grant.
- SECTION § 39.31 - Preapplication requirements.
- SECTION § 39.32 - Plan preparation.
- SECTION § 39.33 - Conferences.
- SECTION § 39.34 - Application requirements.
- SECTION § 39.35 - Final review and approval of application.
- SECTION §§ 39.36-39.49 - §[Reserved]
Award of Grant
Standards and Requirements
Grant Requirements and Procedures
§ 39.30 - General requirements for a grant.
(a) For a State or Tribal Organization to obtain a grant for the establishment, expansion, or improvement of a State or Tribal veterans cemetery:
(1) Its preapplication for the grant must be approved by VA under § 39.31(e);
(2) Its project must be ranked sufficiently high on the priority list in § 39.3 for the applicable fiscal year so that funds are available for the project;
(3) Its plans and specifications for the project must be approved by VA under § 39.32;
(4) The State or Tribal Organization must meet the application requirements in § 39.34; and
(5) Other requirements specified in §§ 39.6, 39.10, and 39.33 must be satisfied.
(b) VA may approve under § 39.35 any application under this subpart up to the amount of the grant requested once the requirements under paragraph (a) of this section have been satisfied, provided that sufficient funds are available. In determining whether sufficient funds are available, VA shall consider the project's priority ranking, the total amount of funds available for cemetery grant awards during the applicable fiscal year, and the prospects of higher ranking projects being ready for the award of a grant before the end of the applicable fiscal year.
§ 39.31 - Preapplication requirements.
(a) A State or Tribal Organization seeking a grant for the establishment, expansion, or improvement of a State or Tribal veterans cemetery must submit a preapplication to the Director, Veterans Cemetery Grants Service, through http://www.cem.va.gov/cem/scg_grants.asp.
(b) No detailed drawings, plans, or specifications are required with the preapplication. As a part of the preapplication, the State or Tribal Organization must submit each of the following:
(1) Standard Form 424 (Application for Federal Assistance) and Standard Form 424C (Budget Information) signed by the authorized representative of the State. These forms document the amount of the grant requested, which may not exceed 100 percent of the estimated cost of the project to be funded with the grant.
(2) A program narrative describing the objectives of the project, the need for a grant, the method of accomplishment, the projected interment rate, and the results or benefits expected to be obtained from the assistance requested.
(3) If a site has been selected, a description of the geographic location of the project (i.e., a map showing the location of the project and all appropriate geographic boundaries, and any other supporting documentation, as needed).
(4) A design concept describing the major features of the project including the number and types of gravesites, such as columbarium niches.
(5) Any comments or recommendations made by the State's or Tribal Organization's “Single Point of Contact” reviewing agency.
(6) VA Form 40-0895-2 (Certification of Compliance with Provisions of the Davis-Bacon Act) to certify that the State or Tribal Organization has obtained the latest prevailing wage rates for Federally funded projects. Any construction project fully or partially funded with Federal dollars must comply with those rates for specific work by trade employees (e.g., electricians, carpenters).
(7) VA Form 40-0895-3 (State or Tribal Government Cemetery Grants Service Space Program Analysis—Buildings) to provide information on the proposed size of cemetery buildings, based on VA guidance on the net and gross square footage standards for cemetery buildings. This standard is based on a workload of 1-6 burials per day.
(8) VA Form 40-0895-6 (Certification of State or Tribal Government Matching Architectural and Engineering Funds to Qualify for Group 1 on the Priority List) to provide documentation that the State or Tribal Organization has authority to support the project and the resources necessary to initially fund the architectural and engineering portion of the project development. Once the grant is awarded, VA will reimburse the applicant for all allowable architectural and engineering costs.
(9) VA Form 40-0895-7 (Certification Regarding Debarment, Suspension, and Other Responsibility Matters—Primary Covered Transactions (State or Tribal Government)) to ensure that the applicant has not been debarred or suspended, and is eligible to participate in the VA grant process and receive Federal funds.
(10) VA Form 40-0895-8 (Certification Regarding Drug-Free Workplace Requirements for Grantees Other Than Individuals) to ensure that the applicant complies with the Drug-Free Workplace Act of 1988 at the location where the construction will occur.
(11) VA Form 40-0895-9 (Certification Regarding Lobbying) to ensure that the applicant complies with Public Law 101-121 regarding the prohibition against any payments to anyone that influences or attempts to influence an officer or Member of Congress in connection with the award of a grant.
(12) VA Form 40-0895-10 (Certification of Compliance with Federal Requirements—State or Tribal Government Construction Grant) to ensure that the applicant complies with all requirements of part 39.
(13) VA Form 40-0895-15 (Certification of Cemetery Maintained in Accordance with National Cemetery Administration Standards) to ensure that any cemetery established, expanded, or improved through a grant will be operated and maintained in accordance with the operational standards of NCA.
(c) In addition, the State or Tribal Organization must submit written assurance of each of the following conditions:
(1) Any cemetery established, expanded, or improved through a grant will be used exclusively for the interment or memorialization of eligible persons, as set forth in § 39.10(a), whose interment or memorialization is not contrary to the conditions of the grant (see § 39.10(b) and 38 U.S.C. 2408(d) and 2411).
(2) Title to the site is or will be vested solely in the State or held in trust for the Tribal Organization on trust land.
(3) The State or Tribal Organization possesses legal authority to apply for the grant and to finance and construct the proposed facilities; i.e., legislation or similar action has been duly adopted or passed as an official act of the applicant's governing body, authorizing the filing of the application, including all understandings and assurances contained therein, and directing and authorizing the person identified as the official representative of the State or Tribal Organization to act in connection with the application and to provide such additional information as may be required.
Note to paragraph (In any case where a Tribal Organization is applying for a grant for a cemetery on land held in trust for more than one Indian Tribe, written assurance that the Tribal Organization possesses legal authority to apply for the grant includes certification that the Tribal Organization has obtained the approval of each such Indian Tribe.
(4) The State or Tribal Organization will assist VA in assuring that the grant complies with section 106 of the National Historic Preservation Act of 1966, as amended (16 U.S.C. 470), Executive Order 11593 (identification and protection of historic properties), and the Archaeological and Historic Preservation Act of 1974 (16 U.S.C. 469a-1 et seq.).
(5) The State or Tribal Organization will obtain approval by VA of the final construction drawings and specifications before the project is advertised or placed on the market for bidding; it will construct the project, or cause the project to be constructed, to completion in accordance with the application and approved plans and specifications; it will submit to the Director of the Veterans Cemetery Grants Service, for prior approval, changes that alter any cost of the project, use of space, or functional layout; and it will not enter into a construction contract for the project or undertake other activities until the requirements of the grant program have been met.
(6) The State or Tribal Organization will comply with the Federal requirements in 2 CFR parts 180, 200, and 801 and submit Standard Form 424D (Assurances—Construction Programs).
(7) The State or Tribal Organization will prepare an Environmental Assessment to determine whether an Environmental Impact Statement is necessary, and certify that funds are available to finance any costs related to preparation of the Environmental Assessment.
(d) The State or Tribal Organization must submit a copy of the State or Tribal Organization action authorizing the establishment, maintenance, and operation of the facility as a veterans cemetery in accordance with 38 CFR 39.10(a). If the State or Tribal Organization action is based on legislation, enacted into law, then the legislation must be submitted.
(e) Upon receipt of a complete preapplication for a grant, including all necessary assurances and all required supporting documentation, VA will determine whether the preapplication conforms to all requirements listed in paragraphs (a) through (d) of this section, including whether it contains sufficient information necessary to establish the project's priority. VA will notify the State or Tribal Organization of any nonconformity. If the preapplication does conform, VA shall notify the State or Tribal Organization that the preapplication has been found to meet the preapplication requirements, and the proposed project will be included in the next scheduled ranking of projects, as indicated in § 39.3(d).
§ 39.32 - Plan preparation.
The State or Tribal Organization must prepare Establishment, Expansion, and Improvement Project plans and specifications in accordance with the requirements of this section for review by the VCGS. The plans and specifications must be approved by the VCGS prior to the State's or Tribal Organization's solicitation for construction bids. Once the VCGS approves the plans and specifications, the State or Tribal Organization must obtain construction bids and determine the successful bidder prior to submission of the application. The State or Tribal Organization must establish procedures for determining that costs are reasonable and necessary and can be allocated in accordance with 2 Cspan part 200. Once the Establishment, Expansion, and Improvement Project preapplication and the project's plans and specifications have been approved, an application for assistance must be submitted in compliance with the uniform requirements for grants-in-aid to State and local governments prescribed by 2 Cspan part 200.
(a) General. These requirements have been established for the guidance of the State or Tribal Organization and the design team to provide a standard for preparation of drawings, specifications, and estimates.
(b) Technical requirements. The State or Tribal Organization should meet these technical requirements as soon as possible after VA approves the Establishment, Expansion, and Improvement Project preapplication.
(1) Boundary and site survey. The State or Tribal Organization shall provide a survey of the site and furnish a legal description of the site. A boundary and site survey need not be submitted if one was submitted for a previously approved project and there have been no changes. Relevant information may then be shown on the site plan. If required, the site survey shall show each of the following items:
(i) The outline and location referenced to boundaries of all existing buildings, streets, alleys (whether public or private), block boundaries, easements, encroachments, the names of streets, railroads, and streams, and other information as specified. If there is nothing of this character affecting the property, the Surveyor shall so state on the drawings.
(ii) The point of beginning, bearing, distances, and interior angles. Closure computations shall be furnished with the survey, and error of closure shall not exceed 1 foot for each 10,000 feet of lineal traverse. Boundaries of an unusual nature (curvilinear, off-set, or having other change or direction between corners) shall be referenced with curve data (including measurement chord) and other data sufficient for replacement, and such information shall be shown on the map. For boundaries of such nature, coordinates shall be given for all angles and other pertinent points.
(iii) The area of the parcel in acres or in square feet.
(iv) The location of all monuments.
(v) Delineation of 100-year floodplain and source.
(vi) The signature and certification of the Surveyor.
(2) Soil investigation. The State or Tribal Organization shall provide a soil investigation of the scope necessary to ascertain site characteristics for construction and burial or to determine foundation requirements and utility service connections. A new soil investigation is not required if one was done for a previously approved project on the same site and information from the previous investigation is adequate and unchanged. Soil investigation, when done, shall be documented in a signed report. The investigation shall be adequate to determine the subsoil conditions. The investigation shall include a sufficient number of test pits or test borings as will determine, in the judgment of the architect, the true conditions. The following information will be covered in the report:
(i) Thickness, consistency, character, and estimated safe bearing value where needed for structural foundation design of the various strata encountered in each pit or boring.
(ii) Amount and elevation of ground water encountered in each pit or boring, its probable variation with the seasons, and effect on the subsoil.
(iii) The elevation of rock, if known, and the probability of encountering quicksand.
(iv) If the site is underlaid with mines, the elevations and location of the tops of the mine workings relative to the site, or old workings located in the vicinity.
(3) Topographical survey. A topographical survey in 1-foot contour intervals shall be prepared for projects establishing new cemeteries and for significant expansion projects in previously undeveloped land.
(c) Master plan. A master plan showing the proposed layout of all facilities—including buildings, roadways, and burial sections—on the selected site shall be prepared for all new cemetery establishment projects for approval by the VCGS. If the project is to be phased into different year programs, the phasing shall be indicated. The master plan shall analyze all factors affecting the design, including climate, soil conditions, site boundaries, topography, views, hydrology, environmental constraints, transportation access, etc. It should provide a discussion of alternate designs that were considered. In the case of an expansion project or improvement project, the work contemplated should be consistent with the VA-approved master plan or a justification for the deviation should be provided.
(d) Preliminary or “design development” drawings. Following VA approval of the master plan, the State or Tribal Organization must submit design development drawings that show all current phase construction elements to be funded by the grant. The drawings must comply with the following requirements:
(1) Site development and environmental plans must include locations of structures, demolition, parking, roads, service areas, walks, plazas, memorial paths, other paved areas, landscape buffer and major groupings, and interment areas (including quantity of gravesites in each area). A grading plan including existing and proposed contours at 1-foot intervals of the entire area affected by the site work must be submitted. A site plan of the immediate area around each building shall be drawn to a convenient scale and shall show the building floor plan, utility connections, walks, gates, walls or fences, flagpoles, drives, parking areas, indication of handicapped provisions, landscaping, north arrow, and any other appropriate items.
(2) Floor plans of all levels at a convenient scale shall be double-line drawings and shall show overall dimensions, construction materials, door swings, names and square feet for each space, toilet room fixtures, and interior finish schedule.
(3) Elevations of the exteriors of all buildings shall be drawn to the same scale as the plan and shall include all material indications.
(4) Preliminary mechanical and electrical layout plans shall be drawn at a convenient scale and shall have an equipment and plumbing fixture schedule.
(e) Final construction drawings and specifications. Funds for the construction of any project being assisted under this program will not be released until VA approves the final construction drawings and specifications. If VA approves them, VA shall send the State or Tribal Organization a written letter of approval indicating that the project's plans and specifications comply with the terms and conditions as prescribed by VA. This does not constitute approval of the contract documents. It is the responsibility of the State or Tribal Organization to ascertain that all State and Federal requirements have been met and that the drawings and specifications are acceptable for bid purposes.
(1) General. The State or Tribal Organization shall prepare final working drawings so that clear and distinct prints may be obtained. These drawings must be accurately dimensioned to include all necessary explanatory notes, schedules, and legends. Working drawings shall be complete and adequate for VA review and comment. The State or Tribal Organization shall prepare separate drawings for each of the following types of work: Architectural, equipment, layout, structural, heating and ventilating, plumbing, and electrical.
(2) Architectural drawings. The State or Tribal Organization shall submit drawings which include: All structures and other work to be removed; all floor plans if any new work is involved; all elevations which are affected by the alterations; building sections; demolition drawings; all details to complete the proposed work and finish schedules; and fully dimensioned floor plans at 1/8″ or 1/4″ scale.
(3) Equipment drawings. The State or Tribal Organization shall submit a list of all equipment to be provided under terms of the grant in the case of an Establishment Project. Large-scale drawings of typical special rooms indicating all fixed equipment and major items of furniture and moveable equipment shall be included.
(4) Layout drawings. The State or Tribal Organization shall submit a layout plan that shows:
(i) All proposed features such as roads, buildings, walks, utility lines, burial layout, etc.
(ii) Contours, scale, north arrow, and legend showing existing trees.
(iii) A graphic or keyed method of showing plant types as well as quantities of each plant.
(iv) Plant list with the following: key, quantity, botanical name, common name, size, and remarks.
(v) Typical tree and shrub planting details.
(vi) Areas to be seeded or sodded.
(vii) Areas to be mulched.
(viii) Gravesite section layout with permanent section monument markers and lettering system.
(ix) Individual gravesite layout and numbering system. If the cemetery is existing and the project is expansion or renovation, show available, occupied, obstructed, and reserved gravesites.
(x) Direction the headstones face.
(5) Structural drawings. The State or Tribal Organization shall submit complete foundation and framing plans and details, with general notes to include: Governing code, material strengths, live loads, wind loads, foundation design values, and seismic zone.
(6) Mechanical drawings. The State or Tribal Organization shall submit:
(i) Heating and ventilation drawings showing complete systems and details of air conditioning, heating, ventilation, and exhaust; and
(ii) Plumbing drawings showing sizes and elevations of soil and waste systems, sizes of all hot and cold water piping, drainage and vent systems, plumbing fixtures, and riser diagrams.
(7) Electrical drawings. The State or Tribal Organization shall submit separate drawings for lighting and power, including drawings of:
(i) Service entrance, feeders, and all characteristics;
(ii) All panel, breaker, switchboard, and fixture schedules;
(iii) All lighting outlets, receptacles, switches, power outlets, and circuits; and
(iv) Telephone layout, fire alarm systems, and emergency lighting.
(8) Final specifications. Final specifications (to be used for bid purposes) shall be in completed format. Specifications shall include the invitations for bids, cover or title sheet, index, general requirements, form of bid bond, form of agreement, performance and payment bond forms, and sections describing materials and workmanship in detail for each class of work.
(9) Cost estimates. The State or Tribal Organization shall show in convenient form and detail the estimated total cost of the work to be performed under the contract, including provisions of fixed equipment shown by the plans and specifications, if applicable, to reflect the changes of the approved financial plan. Estimates shall be summarized and totaled under each trade or type of work. Estimates shall also be provided for each building structure and other important features such as the assembly area and shall include burial facilities.
§ 39.33 - Conferences.
(a) Predesign conference. A predesign conference is required for all Establishment, Expansion, and Improvement Projects requiring major construction, primarily to ensure that the State or Tribal Organization becomes oriented to VA procedures, requirements, and any technical comments pertaining to the project. This conference will take place at an appropriate location near the proposed site and should include a site visit to ensure that all parties to the process, including NCA staff, are familiar with the site and its characteristics.
(b) Additional conferences. At any time, VA may recommend an additional conference (such as a design development conference) be held in VA Central Office in Washington, DC, to provide an opportunity for the State or Tribal Organization and its architects to discuss with VA officials the requirements for a grant.
§ 39.34 - Application requirements.
(a) For an Establishment, Expansion, and Improvement Project to be considered for grant funding under this subpart, the State or Tribal Organization must submit an application (as opposed to a preapplication) consisting of the following:
(1) Standard Form 424 (Application for Federal Assistance) with the box labeled “application” marked;
(2) Standard Form 424C (Budget Information), which documents the amount of funds requested based on the construction costs as estimated by the successful construction bid;
(3) A copy of itemized bid tabulations (If there are non-VA participating areas, these shall be itemized separately.); and
(4) Standard Form 424D (Assurances—Construction Program).
(5) VA Form 40-0895-11 (Memorandum of Agreement for a Grant to Construct or Modify a State or Tribal Government Veterans Cemetery) to identify the parties (VA and applicant), identify the scope of the project, and indicate how the grant award funds will be paid to the applicant.
(6) VA Form 40-0895-12 (Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion—Lower Tier Covered Transactions (Contractor)) to ensure that the contractor has not been debarred or suspended, and is eligible to participate in the VA grant process and receive Federal funds.
(b) Prior to submission of the application, the State or Tribal Organization must submit a copy of an Environmental Assessment to determine if an Environmental Impact Statement is necessary for compliance with section 102(2)(C) of the National Environmental Policy Act of 1969, as amended (42 U.S.C. 4332). The Environmental Assessment must briefly describe the project's possible beneficial and harmful effects on the following impact categories:
(1) Transportation;
(2) Air quality;
(3) Noise;
(4) Solid waste;
(5) Utilities;
(6) Geology (Soils/Hydrology/Floodplains);
(7) Water quality;
(8) Land use;
(9) Vegetation, Wildlife, Aquatic, Ecology/Wetlands, etc.;
(10) Economic activities;
(11) Cultural resources;
(12) Aesthetics;
(13) Residential population;
(14) Community services and facilities;
(15) Community plans and projects; and
(16) Other.
(c) If an adverse environmental impact is anticipated, the State or Tribal Organization must explain what action will be taken to minimize the impact. The assessment shall comply with the requirements of the National Environmental Policy Act of 1969, as amended (42 U.S.C. 4321 et seq.).
§ 39.35 - Final review and approval of application.
Following VA approval of bid tabulations and cost estimates, VA will review the complete Establishment, Expansion and Improvement Project grant application for approval in accordance with the requirements of § 39.30. If the application is approved, the grant will be awarded by a Memorandum of Agreement of Federal grant funds.
§§ 39.36-39.49 - §[Reserved]
Award of Grant
§ 39.50 - Amount of grant.
(a) The amount of an Establishment, Expansion, and Improvement Project grant awarded under this subpart may not exceed 100 percent of the total cost of the project, but may be less than the total cost of the project.
(b) The total cost of a project under this subpart may include:
(1) Administration and design costs, e.g., architectural and engineering fees, inspection fees, and printing and advertising costs.
(2) The cost of cemetery features, e.g., entry features, flag plaza and assembly areas, columbaria, preplaced liners or crypts, irrigation systems, committal-service shelters, and administration/maintenance buildings.
(3) In the case of an establishment grant, the cost of equipment necessary for the operation of the State or Tribal veterans cemetery. This may include the cost of non-fixed equipment such as grounds maintenance equipment, burial equipment, and office equipment.
(4) In the case of an improvement or expansion grant, the cost of equipment necessary for operation of the State or Tribal veterans cemetery, but only if such equipment:
(i) Was included in the construction contract;
(ii) Was installed during construction; and
(iii) Is permanently affixed to a building or connected to the heating, ventilating, air conditioning, or other service distributed through a building via ducts, pipes, wires, or other connecting device, such as kitchen and intercommunication equipment, built-in cabinets, and equipment lifts.
(5) A contingency allowance not to exceed five percent of the total cost of a project that involves new construction or eight percent of the total cost of an improvement project that does not involve new construction.
(c) The total cost of a project under this subpart may not include the cost of:
(1) Land acquisition;
(2) Building space that exceeds the space guidelines specified in this part;
(3) Improvements not on cemetery land, such as access roads or utilities;
(4) Maintenance or repair work;
(5) Office supplies or consumable goods (such as fuel and fertilizer) that are routinely used in a cemetery; or
(6) Fully enclosed, climate-controlled, committal-service facilities, freestanding chapels, or chapels that are part of an administrative building or information center.
(d) VA shall certify approved applications to the Secretary of the Treasury in the amount of the grant, and shall designate the appropriation from which it shall be paid. Funds paid for the establishment, expansion, or improvement of a veterans cemetery must be used solely for carrying out approved projects.
§ 39.51 - Payment of grant award.
The amount of an Establishment, Expansion, and Improvement Project grant award will be paid to the State or Tribal Organization or, if designated by the State or Tribal Organization representative, the State or Tribal veterans cemetery for which such project is being carried out, or to any other State or Tribal Organization agency or instrumentality. Such amount shall be paid by way of reimbursement and in installments that are consistent with the progress of the project, as the Director of the Veterans Cemetery Grants Service may determine and certify for payment to the appropriate Federal institution. Funds paid under this section for an approved Establishment, Expansion, and Improvement Project shall be used solely for carrying out such project as approved. As a condition for the final payment, the representative of the State or Tribal Organization must submit to VA the following:
(a) Standard Form 271 (Outlay Report and Request for Reimbursement for Construction Programs);
(b) A request in writing for the final architectural/engineering inspection, including the name and telephone number of the local point of contact for the project;
(c) The written statement, “It is hereby agreed that the monetary commitment of the Federal government will have been met and the project will be considered terminated upon payment of this voucher.”; and
(d) Evidence that the State or Tribal Organization has met its responsibility for an audit under the Single Audit Act of 1984 (31 U.S.C. 7501 et seq.) and § 39.122, if applicable.
§§ 39.52-39.59 - §[Reserved]
Standards and Requirements
§ 39.60 - General requirements for site selection and construction of veterans cemeteries.
(a) The various codes, requirements, and recommendations of State or Tribal Organization and local authorities or technical and professional organizations, to the extent and manner in which those codes, requirements, and recommendations are referenced in this subpart, are applicable to grants involving construction of veterans cemeteries. Additional information concerning these codes, requirements, and recommendations may be obtained from VA, National Cemetery Administration, 810 Vermont Avenue NW., Washington, DC 20420.
(b) The standards in §§ 39.60, 39.61, 39.62, and 39.63 constitute general design and construction criteria and shall apply to all Establishment, Expansion, and Improvement Projects for which Federal assistance is requested under 38 U.S.C. 2408.
(c) In developing these standards, no attempt has been made to comply with all of the various State and local codes and regulations. The standards contained in §§ 39.60, 39.61, 39.62, and 39.63 shall be followed where they exceed State or local codes and regulations. Departure will be permitted, however, when alternate standards are demonstrated to provide equivalent or better design criteria than the standards in these sections. Conversely, compliance is required with State and local codes where such requirements provide a standard higher than those in these sections. The additional cost, if any, in using standards that are higher than those of VA should be documented and justified in the application.
(d) The space criteria and area requirements referred to in these standards shall be used as a guide in planning. Additional area and facilities beyond those specified as basic may be included if found to be necessary to meet the functional requirements of the project but are subject to approval by VA. Substantial deviation from the space criteria or area standards shall be carefully considered and justified. Failing to meet the criteria or standards or exceeding them by more than 10 percent in the completed plan would be regarded as evidence of inferior design or as exceeding the boundaries of professional requirements. In those projects that unjustifiably exceed maximum space criteria or area requirements, VA funding may be subject to reduction in proportion to the amount by which the space or area of the cemetery exceeds the maximum specified in these standards.
§ 39.61 - Site planning standards.
(a) Site selection—(1) Location. The land should be located as close as possible to the densest veteran population in the area under consideration.
(2) Size. Sufficient acreage shall be available to provide gravesites for estimated needs for at least 20 years. More acreage should be provided where feasible. Acreage could vary depending on the State veteran population and national cemetery availability.
(3) Accessibility. The site should be readily accessible by highway. Offsite improvements shall not be funded by the grant.
(4) Topography. The land should range from comparatively level to rolling and moderately hilly terrain. Natural rugged contours are suitable only if development and maintenance costs would not be excessive and burial areas would be accessible to elderly or infirm visitors. The land shall not be subject to flooding.
(5) Water table. The water table should be lower than the maximum proposed depth of burial.
(6) Soil requirements. The soil should be free from rock, muck, unstable composition, and other materials that would hamper the economical excavation of graves by normal methods. In general, the soil should meet the standards of good agricultural land that is capable of supporting turf and trees, with normal care and without the addition of topsoil.
(7) Utilities. Electricity and gas, if required, should be available. Offsite improvements shall not be funded by the grant.
(8) Water supply. An adequate supply of water should be available. Offsite improvements shall not be funded by the grant.
(9) Sewerage. An approved means to dispose of storm flow and sewage from the facility should be available. Offsite improvements shall not be funded by the grant.
(b) Site development requirements—(1) General. The development plan shall provide for adequate hard-surfaced roads, walks, parking areas, public rest rooms, a flag circle, and a main gate.
(2) Parking. All parking facilities shall include provisions to accommodate the physically handicapped. A minimum of one space shall be set aside and identified with signage in each parking area with additional spaces provided in the ratio of 1 handicapped space to every 20 regular spaces. Handicapped spaces shall not be placed between two conventional diagonal or head-on parking spaces. Each of the handicapped parking spaces shall not be less than 9 feet wide; in addition, a clear space 4 feet wide shall be provided between the adjacent conventional parking spaces and also on the outside of the end spaces. Parking shall not be provided for large numbers of people attending ceremonial events such as Memorial Day services.
(3) Roads. Roads should generally follow the topography of the cemetery and allow pedestrian access to burial sections on both sides. Roads should generally not be used as “boundaries” outlining burial sections. Extensive bridging should be avoided. Grant program funding may not be used to build access roads on property that is not part of the cemetery. Road widths shall be compatible with proposed traffic flows and volumes. Primary roads shall be generally 24 feet wide.
(4) Pavement design. The pavement section of all roads, service areas, and parking areas shall be designed for the maximum anticipated traffic loads and existing soil conditions and in accordance with local and State design criteria.
(5) Curbs. Bituminous roads may be provided with integral curbs and gutters constructed of portland cement concrete. Freestanding curbs may be substituted when the advantage of using them is clearly indicated. All curbs shall have a “roll-type” cross section for vehicle and equipment access to lawn areas except as may be necessary for traffic control. The radii of curbs at road intersections shall not be less than 20 feet-0 inches. Curb ramps shall be provided to accommodate the physically handicapped and maintenance equipment. Curb ramps shall be provided at all intersections of roads and walks. The curb ramps shall not be less than 4 feet wide; they shall not have a slope greater than 8 percent, and preferably not greater than 5 percent. The vertical angle between the surface of a curb ramp and the surface of a road or gutter shall not be less than 176 degrees; the transition between the two surfaces shall be smooth. Curb ramps shall have nonskid surfaces.
(6) Walks. Walks shall be designed with consideration for the physically handicapped and elderly. Walks and ramps designed on an incline shall have periodic level platforms. All walks, ramps and platforms shall have nonskid surfaces. Any walk shall be ramped if the slope exceeds 3 percent. Walks that have gradients from 2 to 3 percent shall be provided with level platforms at 200-foot intervals and at intersections with other walks. Ramps shall not have a slope greater than 8 percent, and preferably not greater than 5 percent. The ramps shall have handrails on both sides unless other protective devices are provided; every handrail shall have clearance of not less than 1 1/2 inches between the back of the handrail and the wall or any other vertical surface behind it. Ramps shall not be less than 4 feet wide between curbs; curbs shall be provided on both sides. The curbs shall not be less than 4 inches high and 4 inches wide. A level platform in a ramp shall not be less than the full width of the ramp and not less than 5 feet long. Entrance platforms and ramps shall be provided with protective weather barriers to shield them against hazardous conditions resulting from inclement weather.
(7) Steps. Exterior steps may be included in the site development as long as provisions are made for use by physically handicapped persons.
(8) Grading. Minimum lawn slopes shall be 2 percent; critical spot grade elevations shall be shown on the contract drawings. Insofar as practicable, lawn areas shall be designed without steep slopes.
(9) Landscaping. The landscaping plan should provide for a park-like setting of harmonious open spaces balanced with groves of indigenous and cultivated deciduous and evergreen trees. Shrubbery should be kept to a minimum. Steep slopes that are unsuitable for interment areas should be kept in their natural state.
(10) Surface drainage. Surface grades shall be determined in coordination with the architectural, structural, and mechanical design of buildings and facilities so as to provide proper surface drainage.
(11) Burial areas. A site plan of the cemetery shall include a burial layout. If appropriate, the burial layout should reflect the phases of development in the various sections. The first phase of construction should contain sufficient burial sites to meet the foreseeable demand for at least 10 years. All applicable dimensions of roadways, fences, utilities, or other structures shall be indicated on the layout.
(12) Gravesites. Gravesites shall be laid out in uniform pattern. There shall be a minimum of 10 feet from the edge of roads and drives and a minimum of 20 feet from the boundaries or fence lines. Maximum distance from the edge of a permanent road to any gravesite shall not be over 275 feet. Temporary roads may be provided to serve areas in phase developments.
(13) Monumentation. Each grave shall be marked with an appropriate marker, and each cemetery shall maintain a register of burials setting forth the name of each person buried and the designation of the grave in which he/she is buried. Permanent gravesite control markers shall be installed based on a grid system throughout the burial area unless otherwise specified. This will facilitate the gravesite layout, placement of utility lines, and alignment of headstones.
(14) Entrance. The entrance should be an architectural or landscape feature that creates a sense of arrival.
(15) Memorial walkway. Each cemetery should have an area for the display of memorials donated by veterans groups and others. Such areas may take the form of a path or walkway and should provide a contemplative setting for visitors.
(16) Donation items. Family members and others often wish to donate items such as benches and trees. Acceptable items of donation should be specified in the cemetery plan. The plan should also designate appropriate locations for such items.
(17) Flag/assembly area. There shall be one primary flagpole for the United States flag. This flag shall be lighted. A turf assembly area should be developed for major gatherings such as Memorial Day. The assembly area may be focused on the flag. The area may also incorporate an architectural or a landscape feature that functions as a platform or backdrop for speakers.
(18) Site furnishings. Site furnishings include signage, trash receptacles, benches, and flower containers. These items should be coordinated and complement each other, the architectural design, and the cemetery as a whole. They should be simple, durable, standardized, and properly scaled.
(19) Carillons. The cemetery development plan should include a location for a carillon tower. Carillons are normally donated. They are not provided for in the grant.
§ 39.62 - Space criteria for support facilities.
These criteria are based on a projected average burial rate of one to six per day, staffing by position, and a defined complement of maintenance and service equipment. For cemeteries with less than one or more than six burials per day, support facilities are considered on an individual basis in accordance with § 39.60(d). In converting Net Square Feet (NSF) to Gross Square Feet (GSF), a conversion factor of 1.5 is the maximum allowed. The applicant shall, in support of the design, include the following as an attachment to the application: A list of all grounds maintenance supplies and equipment and the number of Full Time Employees (FTE) by job assignment for the next 10 years.
(a) Administrative building. The administrative building should be approximately 1,600 NSF in total, providing space, as needed, for the following:
(1) Cemetery director's office;
(2) Other offices (as needed);
(3) Administrative staff (lobby/office area);
(4) Operations (file/office/equipment/work area);
(5) Family/conference room;
(6) Military honors team;
(7) Refreshment unit;
(8) Housekeeping aide's closet; and
(9) Restroom facilities.
(b) Maintenance/service building. The maintenance/service building may be combined with the administrative building. The maintenance/service building should be approximately 2,200 NSF in total, providing heated and air conditioned space, as needed, for the following:
(1) Foreman's office;
(2) Lunch room;
(3) Kitchen unit;
(4) Toilet and locker room facilities;
(5) Housekeeping aide's closet; and
(6) Vehicle and equipment maintenance and storage.
(c) Vehicle and equipment storage. Approximately 275 NSF/Bay as needed. Not all types of vehicles and equipment require storage in heated space. Based on climatic conditions, it may be justified to rely completely on open structures rather than heated structures to protect the following types of vehicles and equipment: Dump trucks, pickup trucks, cemetery automobiles, gang and circular mowers.
(d) Interment/committal service shelter. One permanent shelter is authorized for every five interments per day. The shelter may include a covered area to provide seating for approximately 20 people and an uncovered paved area to provide space for approximately 50 additional people. The shelter may also include a small, enclosed equipment/storage area. Provisions must be made for the playing of Taps by recorded means.
(e) Public Information Center. One permanent Public Information Center is authorized per facility. A Public Information Center is used to orient visitors and funeral corteges. It should include the gravesite locator. The public restrooms may also be combined with this structure. Space determinations for separate structures for public restrooms shall be considered on an individual basis. The Public Information Center, including public restrooms, may be combined with the administrative building.
(f) Other interment structures. Space determinations for other support facilities such as columbaria, preplaced graveliners (or crypts), garden niches, etc., will be considered on an individual basis in accordance with § 39.60(d).
§ 39.63 - Architectural design standards.
The publications listed in this section are incorporated by reference. The Director of the Federal Register approves this incorporation by reference in accordance with 5 U.S.C. 522(a) and 1 CFR part 51. Copies of these publications may be inspected at the office of the Veterans Cemetery Grants Service, National Cemetery Administration, Department of Veterans Affairs, 810 Vermont Avenue NW., Washington, DC 20420 or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call (202) 741-6030 or go to http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html. Copies of the 2003 edition of the National Fire Protection Association Life Safety Code and Errata (NFPA 101), the 2003 edition of the NFPA 5000, Building Construction and Safety Code, and the 2002 edition of the National Electrical Code, NFPA 70, may be obtained from the National Fire Protection Association, Inc. (NFPA), 1 Batterymarch Park, P.O. Box 9101, Quincy, MA 02269-9101, (800) 844-6058 (toll free). Copies of the 2003 edition of the Uniform Mechanical Code and the 2003 edition of the Uniform Plumbing Code may be obtained from the International Association of Plumbing and Mechanical Officials, 5001 E. Philadelphia Street, Ontario, CA 91761-2816. (909) 472-4100 (this is not a toll-free number). The 2002 and 2003 NFPA and IAPMO code publications can be inspected at VA by calling (202) 461-4902 for an appointment.
(a) Architectural and structural requirements—(1) Life Safety Code. Standards must be in accordance with the 2003 edition of the National Fire Protection Association Life Safety Code, NFPA 101. Fire safety construction features not included in NFPA 101 shall be designed in accordance with the requirements of the 2003 edition of the NFPA 5000, Building Construction and Safety Code. Where the adopted codes state conflicting requirements, the NFPA National Fire Codes shall govern.
(2) State and local codes. In addition to compliance with the standards set forth in this section, all applicable local and State building codes and regulations must be observed. In areas not subject to local or State building codes, the recommendations contained in the 2003 edition of the NFPA 5000, Building Construction and Safety Code, shall apply.
(3) Occupational safety and health standards. Applicable standards contained in the Occupational Safety and Health Act of 1970 (29 U.S.C. 651 et seq.) must be observed.
(b) Mechanical requirements. The heating system, boilers, steam system, ventilation system, and air-conditioning system shall be furnished and installed to meet all requirements of the local and State codes and regulations. Where no local or State codes are in force, the 2003 edition of the Uniform Mechanical Code shall apply.
(c) Plumbing requirements. Plumbing systems shall comply with all applicable local and State codes, the requirements of the State Department of Health, and the minimum general standards as set forth in this part. Where no local or State codes are in force, the 2003 edition of the Uniform Plumbing Code shall apply.
(d) Electrical requirements. The installation of electrical work and equipment shall comply with all local and State codes and laws applicable to electrical installations and the minimum general standards set forth in the NFPA 70, National Electrical Code, 2002 edition. The regulations of the local utility company shall govern service connections. Aluminum bus ways shall not be used as a conducting medium in the electrical distribution system.