Collapse to view only § 3179.6 - Venting limitations.

Authorized Flaring and Venting of Gas

§ 3179.101 - Initial production testing.

(a) Gas flared during the initial production test of each completed interval in a well is royalty free until one of the following occurs:

(1) The operator determines that it has obtained adequate reservoir information;

(2) Thirty (30) days have passed since the beginning of the production test, unless the BLM approves a longer test period; or

(3) The operator has flared 50 million cubic feet (MMcf) of gas.

(b) The operator may request a longer test period and must submit its request using a Sundry Notice.

§ 3179.102 - Subsequent well tests.

(a) Gas flared during well tests subsequent to the initial production test is royalty free for a period not to exceed 24 hours, unless the BLM approves or requires a longer test period.

(b) The operator may request a longer test period and must submit its request using a Sundry Notice.

§ 3179.103 - Emergencies.

(a) Gas flared or vented during an emergency is royalty free for a period not to exceed 24 hours, unless the BLM determines that emergency conditions exist necessitating venting or flaring for a longer period.

(b) For purposes of this subpart, an “emergency” is a temporary, infrequent and unavoidable situation in which the loss of gas or oil is uncontrollable or necessary to avoid risk of an immediate and substantial adverse impact on safety, public health, or the environment, and is not due to operator negligence.

(c) The following do not constitute emergencies for the purpose of royalty assessment:

(1) The operator's failure to install appropriate equipment of a sufficient capacity to accommodate the production conditions;

(2) Failure to limit production when the production rate exceeds the capacity of the related equipment, pipeline, or gas plant, or exceeds sales contract volumes of oil or gas;

(3) Scheduled maintenance;

(4) A situation caused by operator negligence, including recurring equipment failures; or

(5) A situation on a lease, unit, or communitized area that has already experienced 3 or more emergencies within the past 30 days, unless the BLM determines that the occurrence of more than 3 emergencies within the 30 day period could not have been anticipated and was beyond the operator's control.

(d) Within 45 days of the start of the emergency, the operator must estimate and report to the BLM on a Sundry Notice the volumes flared or vented beyond the timeframe specified in paragraph (a) of this section.

§ 3179.104 - Downhole well maintenance and liquids unloading.

(a) Gas vented or flared during downhole well maintenance and well purging is royalty free for a period not to exceed 24 hours per event, provided that the requirements of paragraphs (b) through (d) of this section are met. Gas vented or flared from a plunger lift system and/or an automated well control system is royalty free, provided the requirements of paragraphs (b) and (c) of this section are met.

(b) The operator must minimize the loss of gas associated with downhole well maintenance and liquids unloading, consistent with safe operations.

(c) For wells equipped with a plunger lift system and/or an automated well control system, minimizing gas loss under paragraph (b) of this section includes optimizing the operation of the system to minimize gas losses to the extent possible consistent with removing liquids that would inhibit proper function of the well.

(d) For any liquids unloading by manual well purging, the operator must ensure that the person conducting the well purging remains present on-site throughout the event to end the event as soon as practical, thereby minimizing to the maximum extent practicable any venting to the atmosphere.

(e) For purposes of this section, “well purging” means blowing accumulated liquids out of a wellbore by reservoir gas pressure, whether manually or by an automatic control system that relies on real-time pressure or flow, timers, or other well data, where the gas is vented to the atmosphere, and it does not apply to wells equipped with a plunger lift system.

§ 3179.1 - Purpose.

The purpose of this subpart is to implement and carry out the purposes of statutes relating to prevention of waste from Federal and Indian (other than Osage Tribe) leases, conservation of surface resources, and management of the public lands for multiple use and sustained yield. This subpart supersedes those portions of Notice to Lessees and Operators of Onshore Federal and Indian Oil and Gas Leases, Royalty or Compensation for Oil and Gas Lost (NTL-4A), pertaining to, among other things, flaring and venting of produced gas, unavoidably and avoidably lost gas, and waste prevention.

§ 3179.2 - Scope.

(a) This subpart applies to:

(1) All onshore Federal and Indian (other than Osage Tribe) oil and gas leases, units, and communitized areas, except as otherwise provided in this subpart;

(2) IMDA oil and gas agreements, unless specifically excluded in the agreement or unless the relevant provisions of this subpart are inconsistent with the agreement;

(3) Leases and other business agreements and contracts for the development of tribal energy resources under a Tribal Energy Resource Agreement entered into with the Secretary, unless specifically excluded in the lease, other business agreement, or Tribal Energy Resource Agreement;

(4) Committed State or private tracts in a federally approved unit or communitization agreement defined by or established under 43 CFR part 3100, subpart 3105, or 43 CFR part 3180; and

(5) All onshore well facilities located on a Federal or Indian lease or a federally approved unit or communitized area.

(b) For purposes of this subpart, the term “lease” also includes IMDA agreements.

§ 3179.3 - Definitions and acronyms.

As used in this subpart, the term:

Automatic ignition system means an automatic ignitor and, where needed to ensure continuous combustion, a continuous pilot flame.

Capture means the physical containment of natural gas for transportation to market or productive use of natural gas, and includes injection and royalty-free on-site uses pursuant to subpart 3178 of this part.

Gas-to-oil ratio (GOR) means the ratio of gas to oil in the production stream expressed in standard cubic feet of gas per barrel of oil.

Gas well means a well for which the energy equivalent of the gas produced, including its entrained liquefiable hydrocarbons, exceeds the energy equivalent of the oil produced, as determined at the time of well completion.

Liquids unloading means the removal of an accumulation of liquid hydrocarbons or water from the wellbore of a completed gas well.

Lost oil or lost gas means produced oil or gas that escapes containment, either intentionally or unintentionally, or is flared before being removed from the lease, unit, or communitized area, and cannot be recovered.

Oil well means a well for which the energy equivalent of the oil produced exceeds the energy equivalent of the gas produced, as determined at the time of well completion.

Waste of oil or gas means any act or failure to act by the operator that is not sanctioned by the authorized officer as necessary for proper development and production, where compliance costs are not greater than the monetary value of the resources they are expected to conserve, and which results in:

(1) A reduction in the quantity or quality of oil and gas ultimately producible from a reservoir under prudent and proper operations; or

(2) Avoidable surface loss of oil or gas.

§ 3179.4 - Determining when the loss of oil or gas is avoidable or unavoidable.

For purposes of this subpart:

(a) Avoidably lost production means:

(1) Gas that is vented or flared without the authorization or approval of the BLM; or

(2) Produced oil or gas that is lost when the BLM determines that such loss occurred as a result of:

(i) Negligence on the part of the operator;

(ii) The failure of the operator to take all reasonable measures to prevent or control the loss; or

(iii) The failure of the operator to comply fully with the applicable lease terms and regulations, appropriate provisions of the approved operating plan, or prior written orders of the BLM.

(b) Unavoidably lost production means:

(1) Oil or gas that is lost because of line failures, equipment malfunctions, blowouts, fires, or other similar circumstances, except where the BLM determines that the loss was avoidable pursuant to paragraph (a)(2) of this section;

(2) Oil or gas that is lost from the following operations or sources, except where the BLM determines that the loss was avoidable pursuant to paragraph (a)(2) of this section:

(i) Well drilling;

(ii) Well completion and related operations;

(iii) Initial production tests, subject to the limitations in § 3179.101;

(iv) Subsequent well tests, subject to the limitations in § 3179.102;

(v) Exploratory coalbed methane well dewatering;

(vi) Emergencies, subject to the limitations in § 3179.103;

(vii) Normal gas vapor losses from a storage tank or other low pressure production vessel, unless the BLM determines that recovery of the gas vapors is warranted;

(viii) Well venting in the course of downhole well maintenance and/or liquids unloading performed in compliance with § 3179.104; or

(ix) Facility and pipeline maintenance, such as when an operator must blow-down and depressurize equipment to perform maintenance or repairs; or

(3) Produced gas that is flared or vented with BLM authorization or approval.

§ 3179.5 - When lost production is subject to royalty.

(a) Royalty is due on all avoidably lost oil or gas.

(b) Royalty is not due on any unavoidably lost oil or gas.

§ 3179.6 - Venting limitations.

(a) Gas well gas may not be flared or vented, except where it is unavoidably lost pursuant to § 3179.4(b).

(b) The operator must flare, rather than vent, any gas that is not captured, except:

(1) When flaring the gas is technically infeasible, such as when the gas is not readily combustible or the volumes are too small to flare;

(2) Under emergency conditions, as defined in § 3179.105, when the loss of gas is uncontrollable or venting is necessary for safety;

(3) When the gas is vented through normal operation of a natural gas-activated pneumatic controller or pump;

(4) When gas vapor is vented from a storage tank or other low pressure production vessel, unless the BLM determines that recovery of the gas vapors is warranted;

(5) When the gas is vented during downhole well maintenance or liquids unloading activities;

(6) When the gas venting is necessary to allow non-routine facility and pipeline maintenance to be performed, such as when an operator must, upon occasion, blow-down and depressurize equipment to perform maintenance or repairs; or

(7) When a release of gas is unavoidable under § 3179.4 and flaring is prohibited by Federal, State, local or tribal law, regulation, or enforceable permit term.

(c) For purposes of this subpart, all flares or combustion devices must be equipped with an automatic ignition system.

Other Venting or Flaring

§ 3179.201 - Oil-well gas.

(a) Except as provided in §§ 3179.101, 3179.102, 3179.103, and 3179.104, vented or flared oil-well gas is royalty free if it is vented or flared pursuant to applicable rules, regulations, or orders of the appropriate State regulatory agency or tribe. Applicable State or tribal rules, regulations, or orders are appropriate if they place limitations on the venting and flaring of oil-well gas, including through general or qualified prohibitions, volume or time limitations, capture percentage requirements, or trading mechanisms.

(b) With respect to production from Indian leases, vented or flared oil-well gas will be treated as royalty free pursuant to paragraph (a) of this section only to the extent it is consistent with the BLM's trust responsibility.

(c) Except as otherwise provided in this subpart, oil-well gas may not be vented or flared royalty free unless the BLM approves it in writing. The BLM may approve an application for royalty-free venting or flaring of oil-well gas if it determines that it is justified by the operator's submission of either:

(1) An evaluation report supported by engineering, geologic, and economic data that demonstrates to the BLM's satisfaction that the expenditures necessary to market or beneficially use such gas are not economically justified. If flaring exceeds 10 MMcf per well during any month, the BLM may determine that the gas is avoidably lost and therefore subject to royalty; or

(2) An action plan showing how the operator will minimize the venting or flaring of the oil-well gas within 1 year. An operator may apply for approval of an extension of the 1-year time limit, if justified. If the operator fails to implement the action plan, the gas vented or flared during the time covered by the action plan will be subject to royalty. If flaring exceeds 10 MMcf per well during any month, the BLM may determine that the gas is avoidably lost and therefore subject to royalty.

(d) The evaluation report in paragraph (c)(1) of this section:

(1) Must include all appropriate engineering, geologic, and economic data to support the applicant's determination that marketing or using the gas is not economically viable. The information provided must include the applicant's estimates of the volumes of oil and gas that would be produced to the economic limit if the application to vent or flare were approved and the volumes of the oil and gas that would be produced if the applicant was required to market or use the gas. When evaluating the feasibility of marketing or using of the gas, the BLM will determine whether the operator can economically operate the lease if it is required to market or use the gas, considering the total leasehold production, including both oil and gas, as well as the economics of a field-wide plan; and

(2) The BLM may require the operator to provide an updated evaluation report as additional development occurs or economic conditions improve, but no more than once a year.

(e) An approval to flare royalty free, which is in effect as of November 27, 2018, will continue in effect unless:

(1) The approval is no longer necessary because the venting or flaring is authorized by the applicable rules, regulations, or orders of an appropriate State regulatory agency or tribe, as provided in paragraph (a) of this section; or

(2) The BLM requires an updated evaluation report under paragraph (d)(2) of this section and determines to amend or revoke its approval.

Measurement and Reporting Responsibilities

§ 3179.301 - Measuring and reporting volumes of gas vented and flared.

(a) The operator must estimate or measure all volumes of lost oil and gas, whether avoidably or unavoidably lost, from wells, facilities and equipment on a lease, unit PA, or communitized area and report those volumes under applicable ONRR reporting requirements.

(b) The operator may:

(1) Estimate or measure vented or flared gas in accordance with applicable rules, regulations, or orders of the appropriate State or tribal regulatory agency;

(2) Estimate the volume of the vented or flared gas based on the results of a regularly performed GOR test and measured values for the volumes of oil production and gas sales, to allow BLM to independently verify the volume, rate, and heating value of the flared gas; or

(3) Measure the volume of the flared gas.

(c) The BLM may require the installation of additional measurement equipment whenever it is determined that the existing methods are inadequate to meet the purposes of this subpart.

(d) The operator may combine gas from multiple leases, unit PAs, or communitized areas for the purpose of flaring or venting at a common point, but must use a method approved by the BLM to allocate the quantities of the vented or flared gas to each lease, unit PA, or communitized area.

Additional Deference to Tribal Regulations

§ 3179.401 - Deference to tribal regulations.

(a) A tribe that has rules, regulations, or orders that are applicable to any of the matters addressed in this subpart may seek approval from the BLM to have such rules, regulations, or orders apply in place of any or all of the provisions of this subpart with respect to lands and minerals over which that tribe has jurisdiction.

(b) The BLM will approve a tribe's request under paragraph (a) to the extent that it is consistent with the BLM's trust responsibility.

(c) The deference to tribal rules, regulations, or orders provided for in this section is supplemental to, and does not limit, the deference to tribal rules, regulations, or orders provided for in § 3179.201.