Collapse to view only § 3261.17 - How do I amend my operations plan or drilling permit?

§ 3261.10 - How do I get approval to begin well pad construction?

(a) If you do not have an approved geothermal drilling permit, Form 3260-2, apply using a completed and signed Sundry Notice, Form 3260-3, to build well pads and access roads. Send us a complete operations plan (see § 3261.12) and an acceptable bond with your Sundry Notice. You may start well pad construction after we approve your Sundry Notice.

(b) If you already have an approved drilling permit and you have provided an acceptable bond, you do not need any further permission from BLM to start well pad construction, unless you intend to change something in the approved permit. If you propose a change in an approved permit, send us a completed and signed Sundry Notice so we may review your proposed change. Do not proceed with the change until we approve your Sundry Notice.

§ 3261.11 - How do I apply for approval of drilling operations and well pad construction?

(a) Send to BLM:

(1) A completed and signed drilling permit application, Form 3260-2;

(2) A complete operations plan (§ 3261.12);

(3) A complete drilling program (§ 3261.13); and

(4) An acceptable bond (§ 3261.18).

(b) Do not start any drilling operations until after BLM approves the permit.

§ 3261.12 - What is an operations plan?

An operations plan describes how you will drill for and test the geothermal resources covered by your lease. Your plan must tell BLM enough about your proposal to allow us to assess the environmental impacts of your operations. This information should generally include:

(a) Well pad layout and design;

(b) A description of existing and planned access roads;

(c) A description of any ancillary facilities;

(d) The source of drill pad and road building material;

(e) The water source;

(f) A statement describing surface ownership;

(g) A description of procedures to protect the environment and other resources;

(h) Plans for surface reclamation; and

(i) Any other information that BLM may require.

§ 3261.13 - What is a drilling program and how do I apply for drilling program approval?

(a) A drilling program describes all the operational aspects of your proposal to drill, complete, and test a well.

(b) Send to BLM:

(1) A detailed description of the equipment, materials, and procedures you will use;

(2) The proposed/anticipated depth of the well;

(3) If you plan to directionally drill your well, also send us:

(i) The proposed bottom hole location and distances from the nearest section or tract lines;

(ii) The kick-off point;

(iii) The direction of deviation;

(iv) The angle of build-up and maximum angle; and

(v) Plan and cross section maps indicating the surface and bottom hole locations;

(4) The casing and cementing program;

(5) The circulation media (mud, air, foam, etc.);

(6) A description of the logs that you will run;

(7) A description and diagram of the blowout prevention equipment you will use during each phase of drilling;

(8) The expected depth and thickness of fresh water zones;

(9) Anticipated lost circulation zones;

(10) Anticipated reservoir temperature and pressure;

(11) Anticipated temperature gradient in the area;

(12) A plat certified by a licensed surveyor showing the surveyed surface location and distances from the nearest section or tract lines;

(13) Procedures and durations of well testing; and

(14) Any other information we may require.

§ 3261.14 - When must I give BLM my operations plan?

Send us a complete operations plan before you begin any surface disturbance on a lease. You do not need to submit an operations plan for subsequent well operations or altering existing production equipment, unless these activities will cause more surface disturbance than originally approved, or we notify you that you must submit an operations plan. Do not start any activities that will result in surface disturbance until we approve your drilling permit or Sundry Notice.

§ 3261.15 - Must I give BLM my drilling permit application, drilling program, and operations plan at the same time?

You may submit your completed and signed drilling permit application and complete drilling program and operations plan either together or separately.

(a) If you submit them together and we approve your drilling permit, the approved drilling permit will authorize both the pad construction and the drilling and testing of the well.

(b) If you submit the operations plan separately from the drilling permit application and program, you must:

(1) Submit the operations plan before the drilling permit application and drilling program to allow BLM time to comply with National Environmental Policy Act (NEPA); and

(2) Submit a completed and signed Sundry Notice for well pad and access road construction. Do not begin construction until we approve your Sundry Notice.

§ 3261.16 - Can my operations plan, drilling permit, and drilling program apply to more than one well?

(a) Your operations plan and drilling program can sometimes be combined to cover several wells, but your drilling permit cannot. To include more than one well in your operations plan, give us adequate information for all well sites, and we will combine your plan to cover those well sites that are in areas of similar geology and environment.

(b) Your drilling program may also apply to more than one well, provided you will drill the wells in the same manner, and you expect to encounter similar geologic and reservoir conditions.

(c) You must submit a separate geothermal drilling permit application for each well.

§ 3261.17 - How do I amend my operations plan or drilling permit?

(a) If BLM has not yet approved your operations plan or drilling permit, send us your amended plan and completed and signed permit application.

(b) To amend an approved operations plan or drilling permit, submit a completed and signed Sundry Notice describing your proposed change. Do not start any amended operations until after BLM approves your drilling permit or Sundry Notice.

§ 3261.18 - Do I need to file a bond with BLM before I build a well pad or drill a well?

Before starting any operation, you must:

(a) File with BLM either a surety or personal bond in the following minimum amount:

(1) $10,000 for a single lease;

(2) $50,000 for all of your operations within a state; or

(3) $150,000 for all of your operations nationwide;

(b) Get our approval of your surety or personal bond; and

(c) To cover any drilling operations on all leases committed to a unit, either submit a bond for that unit in an amount we specify, or provide a rider to a statewide or nationwide bond specifically covering the unit in an amount we specify.

(d) See subparts 3214 and 3215 for additional details on bonding procedures.

§ 3261.19 - When will BLM release my bond?

BLM will release your bond after you request it and we determine that you have:

(a) Plugged and abandoned all wells;

(b) Reclaimed the surface and other resources; and

(c) Met all the requirements of § 3200.4.

§ 3261.20 - How will BLM review applications submitted under this subpart and notify me of its decision?

(a) When we receive your operations plan, we will make sure it is complete and review it for compliance with the requirements of § 3200.4.

(b) If another Federal agency manages the surface of your lease, we will consult with it before we approve your drilling permit.

(c) We will review your drilling permit and drilling program or your Sundry Notice for well pad construction, to make sure they conform with your operations plan and any mitigation measures we developed while reviewing your plan.

(d) We will check your drilling permit and drilling program for technical adequacy and may require additional information.

(e) We will check your drilling permit for compliance with the requirements of § 3200.4.

(f) If we need any further information to complete our review, we will contact you in writing and suspend our review until we receive the information.

(g) After our review, we will notify you as to whether your permit has been approved or denied, as well as any conditions of approval.

§ 3261.21 - How do I get approval to change an approved drilling operation?

(a) Send BLM a Sundry Notice, form 3260-3, describing the proposed changes. Do not proceed with the changes until we have approved them in writing, except as provided in paragraph (c) of this section. If your operations such as redrilling, deepening, drilling a new directional leg, or plugging back a well would significantly change your approved permit, BLM may require you to send us a new drilling permit (see 43 CFR 3261.13). A significant change would be, for example, redrilling the well to a completely different target, especially a target in an unknown area.

(b) If your changed drilling operation would cause additional surface disturbance, we may also require you to submit an amended operations plan.

(c) If immediate action is required to properly continue drilling operations, or to protect public health, safety, property or the environment, BLM may provide oral approval to change an approved drilling operation. However, you must submit a written Sundry Notice within 48 hours after we orally approve your change.

§ 3261.22 - How do I get approval for subsequent well operations?

Send BLM a Sundry Notice describing your proposed operation. For some routine work, such as cleanouts, surveys, or general maintenance (see § 3264.11(b)), we may waive the Sundry Notice requirement. Contact your local BLM office to ask about waivers for subsequent well operations. Unless you receive a waiver, you must submit a Sundry Notice. Do not start your operations until we grant a waiver or approve the Sundry Notice.