Collapse to view only § 3263.14 - May BLM require me to abandon a well?

§ 3263.10 - May I abandon a well without BLM's approval?

(a) You must have a BLM-approved Sundry Notice documenting your plugging and abandonment program before you start abandoning any well.

(b) You must also notify the local BLM office before you begin abandonment activities, so that we may witness the work. Contact your local BLM office before starting to abandon your well to find out what notification we need.

§ 3263.11 - What information must I give BLM to approve my Sundry Notice for abandoning a well?

Send us a Sundry Notice with:

(a) All the information required in the well completion report (see § 3264.10), unless we already have that information;

(b) A detailed description of the proposed work, including:

(1) Type, depth, length, and interval of plugs;

(2) Methods you will use to verify the plugs (tagging, pressure testing, etc.);

(3) Weight and viscosity of mud that you will use in the uncemented portions;

(4) Perforating or removing casing; and

(5) Restoring the surface; and

(c) Any other information that we may require.

§ 3263.12 - How will BLM review my Sundry Notice to abandon my well and notify me of their decision?

(a) When BLM receives your Sundry Notice, we will make sure it is complete and review it for compliance with the requirements of § 3200.4. We will notify you if we need more information or require additional procedures. If we need any further information to complete our review, we will contact you in writing and suspend our review until we receive the information. If we approve your Sundry Notice, we will send you an approved copy once our review is complete. Do not start abandonment of the well until we approve your Sundry Notice.

(b) BLM may orally approve plugging procedures for a well requiring immediate action. If we do, you must submit the information required in § 3263.11 within 48 hours after we give oral approval.

§ 3263.13 - What must I do to restore the site?

You must remove all equipment and materials and restore the site according to the terms of your permit or other BLM approval.

§ 3263.14 - May BLM require me to abandon a well?

If we determine that your well is no longer needed for geothermal resource production, injection, or monitoring, or if we determine that the well is not mechanically sound, BLM may order you to abandon the well. In either case, if you disagree you may explain to us why the well should not be abandoned. We will consider your reasons before we issue any final order.

§ 3263.15 - May I abandon a producible well?

(a) You may abandon a producible well only after you receive BLM's approval. Before abandoning a producing well, send BLM the information listed in § 3263.11. We may also require you to explain why you want to abandon the well.

(b) BLM will deny your request if we determine that the well is needed:

(1) To protect a Federal lease from drainage; or

(2) To protect the environment or other resources of the United States.