Collapse to view only § 3277.10 - When will BLM inspect my operations?

§ 3277.10 - When will BLM inspect my operations?

BLM may inspect all operations to ensure compliance with the requirements of § 3200.4. You must give us access during normal operating hours to inspect all facilities utilizing Federal geothermal resources.

§ 3277.11 -

(a) The operator or facility operator must keep all records and information pertaining to the operation of your utilization facility, royalty and production meters, and safety training available for BLM inspection for a period of 6 years following the time the records and information are created.

(b) This requirement also pertains to records and information from meters located off your lease or unit, when BLM needs them to determine:

(1) Resource production to a utilization facility; or

(2) The allocation of resource production to your lease or unit.

(c) Store all of these records in a place where they are conveniently available.

§ 3277.12 - What will BLM do if I do not comply with all BLM requirements pertaining to utilization operations?

(a) We will issue you a written Incident of Noncompliance, directing you to take required corrective action within a specific time period. If the noncompliance continues or is serious in nature, BLM will take one or more of the following actions:

(1) Enter the lease, and correct any deficiencies at your expense;

(2) Collect all or part of your bond;

(3) Order modification or shutdown of your operations; and

(4) Take other enforcement action against a lessee who is ultimately responsible for the noncompliance.

(b) Noncompliance may result in BLM terminating your lease (see §§ 3213.17 through 3213.19).