Collapse to view only § 633.19 - Exclusion from the project management oversight program.

§ 633.11 - Covered projects.

(a) The recipient is using funds made available under Chapter 53 of Title 49, United States Code, or any other provision of Federal law; and

(b) The project is a major capital project.

§ 633.13 - Initiation of project management oversight services.

Project management oversight services will be initiated as soon as practicable, once the Administrator determines that this part applies. In most cases, this means that project management oversight will begin during the project development phase of the project, generally after the locally preferred alternative has been chosen (if applicable), unless the Administrator determines it more appropriate to begin oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight.

§ 633.15 - Access to information.

A recipient for a major capital project shall provide the Administrator and the project management oversight contractor chosen under this part access to its records and construction sites, as reasonably may be required.

§ 633.17 - Project management oversight contractor eligibility.

(a) Any person or entity may provide project management oversight services in connection with a major capital project, with the following exceptions:

(1) An entity may not provide project management oversight services for its own project; and

(2) An entity may not provide project management oversight services for a project if there exists a conflict of interest.

(b) In choosing private sector persons or entities to provide project management oversight services, the Administrator uses the procurement requirements in the government-wide procurement regulations, found at Chapter 1 of title 48, Code of Federal Regulations.

§ 633.19 - Exclusion from the project management oversight program.

The Administrator may, in compelling circumstances, determine that a project meeting the criteria of § 633.5(e)(1) is not a major capital project because project management oversight under this part will not benefit the Federal government or the recipient. Typically, this means a project that:

(a) Involves a recipient whose past record indicates the appropriateness of excluding the project from project management oversight under this part; and

(b) Involves such a greater level of financial risk to the recipient than to the Federal government that project management oversight under this part is made less necessary to secure the recipient's diligence.