Collapse to view only § 633.23 - FTA review of a project management plan.

§ 633.21 - Basic requirement.

(a) If a project meets the definition of major capital project, the recipient shall submit a project management plan prepared in accordance with § 633.25, as a condition of Federal financial assistance.

(b)(1) The Administrator will notify the recipient when the recipient must submit the project management plan. Normally, the Administrator will notify the recipient sometime during the project development phase. If the Administrator determines the project is a major capital project after the project development phase, the Administrator will inform the recipient of the determination as soon as possible.

(2) Once the Administrator has notified the recipient that it must submit a project management plan, the recipient will have a minimum of 90 days to submit the plan.

§ 633.23 - FTA review of a project management plan.

Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:

(a) The plan is approved;

(b) The plan is disapproved, including the reasons for the disapproval;

(c) The plan will require modification, as specified, before approval; or

(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.

§ 633.25 - Contents of a project management plan.

A project management plan must be tailored to the type, costs, complexity, and phase of the major capital project, and to the recipient's management capacity and capability. A project management plan must be written to a level of detail sufficient to enable the recipient to determine whether the necessary staff and processes are in place to control the scope, budget, schedule, and quality of the project, while managing the safety and security of all persons. A project management plan must be developed with a sufficient level of detail to enable the Administrator to assess the adequacy of the recipient's plan. At a minimum, a recipient's project management plan must include:

(a) Adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;

(b) A budget covering the project management organization, appropriate contractors and consultants, property acquisition, utility relocation, systems demonstration staff, audits, contingencies, and miscellaneous payments as the recipient may be prepared to justify;

(c) A construction schedule for the project;

(d) A document control procedure and recordkeeping system;

(e) A change order procedure that includes a documented, systematic approach to the handling of construction change orders;

(f) A description of organizational structures, management skills, and staffing levels required throughout the construction phase;

(g) Quality control and quality assurance functions, procedures, and responsibilities for project design, procurement, construction, system installation, and integration of system components;

(h) Material testing policies and procedures;

(i) Internal plan implementation and reporting requirements including cost and schedule control procedures;

(j) Criteria and procedures to be used for testing the operational system or its major components;

(k) Periodic updates of the project management plan, especially related to project budget and schedule, financing, ridership estimates, and the status of local efforts to enhance ridership where ridership estimates partly depend on the success of those efforts;

(l) The recipient's commitment to submit a project budget and project schedule to the Administrator quarterly;

(m) Safety and security management; and

(n) Management of risks, contingencies, and insurance.

§ 633.27 - Implementation of a project management plan.

(a) Upon approval of a project management plan by the Administrator the recipient shall begin implementing the plan.

(b) Generally, a project management plan must be modified if the project is at a new phase or if there have been significant changes identified. If a recipient must modify an approved project management plan, the recipient shall submit the proposed changes to the Administrator along with an explanation of the need for the changes.

(c) A recipient shall submit periodic updates of the project management plan to the Administrator. Such updates shall include, but not be limited to:

(1) Project budget;

(2) Project schedule;

(3) Financing, both capital and operating;

(4) Ridership estimates, including operating plan; and

(5) Where applicable, the status of local efforts to enhance ridership when estimates are contingent, in part, upon the success of such efforts.

(d) A recipient shall submit current data on a major capital project's budget and schedule to the Administrator on a quarterly basis for the purpose of reviewing compliance with the project management plan, except that the Administrator may require submission more frequently than on a quarterly basis if the recipient fails to meet the requirements of the project management plan and the project is at risk of materially exceeding its budget or falling behind schedule. Budget and schedule changes will be analyzed on a case-by-case basis, but FTA generally will consider any cost increase or schedule delay exceeding five percent as a material change. Oversight of projects monitored more frequently than quarterly will revert to quarterly oversight once the recipient has demonstrated compliance with the project management plan and the project is no longer at risk of materially exceeding its budget or falling behind schedule.

§ 633.29 - [Reserved]