Collapse to view only § 824i. Interconnection authority
- § 824. Declaration of policy; application of subchapter
- § 824a. Interconnection and coordination of facilities; emergencies; transmission to foreign countries
- § 824a-1. Pooling
- § 824a-2. Reliability
- § 824a-3. Cogeneration and small power production
- § 824a-4. Seasonal diversity electricity exchange
- § 824b. Disposition of property; consolidations; purchase of securities
- § 824c. Issuance of securities; assumption of liabilities
- § 824d. Rates and charges; schedules; suspension of new rates; automatic adjustment clauses
- § 824e. Power of Commission to fix rates and charges; determination of cost of production or transmission
- § 824f. Ordering furnishing of adequate service
- § 824g. Ascertainment of cost of property and depreciation
- § 824h. References to State boards by Commission
- § 824i. Interconnection authority
- § 824j. Wheeling authority
- § 824j-1. Open access by unregulated transmitting utilities
- § 824k. Orders requiring interconnection or wheeling
- § 824l. Information requirements
- § 824m. Sales by exempt wholesale generators
- § 824n. Repealed.
- § 824o. Electric reliability
- § 824o-1. Critical electric infrastructure security
- § 824p. Siting of interstate electric transmission facilities
- § 824q. Native load service obligation
- § 824r. Protection of transmission contracts in the Pacific Northwest
- § 824s. Transmission infrastructure investment
- § 824s-1. Incentives for cybersecurity investments
- § 824t. Electricity market transparency rules
- § 824u. Prohibition on filing false information
- § 824v. Prohibition of energy market manipulation
- § 824w. Joint boards on economic dispatch
It is declared that the business of transmitting and selling electric energy for ultimate distribution to the public is affected with a public interest, and that Federal regulation of matters relating to generation to the extent provided in this subchapter and subchapter III of this chapter and of that part of such business which consists of the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce is necessary in the public interest, such Federal regulation, however, to extend only to those matters which are not subject to regulation by the States.
For the purpose of this subchapter, electric energy shall be held to be transmitted in interstate commerce if transmitted from a State and consumed at any point outside thereof; but only insofar as such transmission takes place within the United States.
The term “sale of electric energy at wholesale” when used in this subchapter, means a sale of electric energy to any person for resale.
The term “public utility” when used in this subchapter and subchapter III of this chapter means any person who owns or operates facilities subject to the jurisdiction of the Commission under this subchapter (other than facilities subject to such jurisdiction solely by reason of section 824e(e), 824e(f),1
No provision in this subchapter shall apply to, or be deemed to include, the United States, a State or any political subdivision of a State, an electric cooperative that receives financing under the Rural Electrification Act of 1936 (7 U.S.C. 901 et seq.) or that sells less than 4,000,000 megawatt hours of electricity per year, or any agency, authority, or instrumentality of any one or more of the foregoing, or any corporation which is wholly owned, directly or indirectly, by any one or more of the foregoing, or any officer, agent, or employee of any of the foregoing acting as such in the course of his official duty, unless such provision makes specific reference thereto.
For the purpose of assuring an abundant supply of electric energy throughout the United States with the greatest possible economy and with regard to the proper utilization and conservation of natural resources, the Commission is empowered and directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy, and it may at any time thereafter, upon its own motion or upon application, make such modifications thereof as in its judgment will promote the public interest. Each such district shall embrace an area which, in the judgment of the Commission, can economically be served by such interconnection and coordinated electric facilities. It shall be the duty of the Commission to promote and encourage such interconnection and coordination within each such district and between such districts. Before establishing any such district and fixing or modifying the boundaries thereof the Commission shall give notice to the State commission of each State situated wholly or in part within such district, and shall afford each such State commission reasonable opportunity to present its views and recommendations, and shall receive and consider such views and recommendations.
Whenever the Commission, upon application of any State commission or of any person engaged in the transmission or sale of electric energy, and after notice to each State commission and public utility affected and after opportunity for hearing, finds such action necessary or appropriate in the public interest it may by order direct a public utility (if the Commission finds that no undue burden will be placed upon such public utility thereby) to establish physical connection of its transmission facilities with the facilities of one or more other persons engaged in the transmission or sale of electric energy, to sell energy to or exchange energy with such persons: Provided, That the Commission shall have no authority to compel the enlargement of generating facilities for such purposes, nor to compel such public utility to sell or exchange energy when to do so would impair its ability to render adequate service to its customers. The Commission may prescribe the terms and conditions of the arrangement to be made between the persons affected by any such order, including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them.
During the continuance of any emergency requiring immediate action, any person or municipality engaged in the transmission or sale of electric energy and not otherwise subject to the jurisdiction of the Commission may make such temporary connections with any public utility subject to the jurisdiction of the Commission or may construct such temporary facilities for the transmission of electric energy in interstate commerce as may be necessary or appropriate to meet such emergency, and shall not become subject to the jurisdiction of the Commission by reason of such temporary connection or temporary construction: Provided, That such temporary connection shall be discontinued or such temporary construction removed or otherwise disposed of upon the termination of such emergency: Provided further, That upon approval of the Commission permanent connections for emergency use only may be made hereunder.
After six months from August 26, 1935, no person shall transmit any electric energy from the United States to a foreign country without first having secured an order of the Commission authorizing it to do so. The Commission shall issue such order upon application unless, after opportunity for hearing, it finds that the proposed transmission would impair the sufficiency of electric supply within the United States or would impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Commission. The Commission may by its order grant such application in whole or in part, with such modifications and upon such terms and conditions as the Commission may find necessary or appropriate, and may from time to time, after opportunity for hearing and for good cause shown, make such supplemental orders in the premises as it may find necessary or appropriate.
The ownership or operation of facilities for the transmission or sale at wholesale of electric energy which is (a) generated within a State and transmitted from the State across an international boundary and not thereafter transmitted into any other State, or (b) generated in a foreign country and transmitted across an international boundary into a State and not thereafter transmitted into any other State, shall not make a person a public utility subject to regulation as such under other provisions of this subchapter. The State within which any such facilities are located may regulate any such transaction insofar as such State regulation does not conflict with the exercise of the Commission’s powers under or relating to subsection (e).
The Secretary, in consultation with the Commission, may, from time to time, request the reliability councils established under section 202(a) of the Federal Power Act [16 U.S.C. 824a(a) of this title] or other appropriate persons (including Federal agencies) to examine and report to him concerning any electric utility reliability issue. The Secretary shall report to the Congress (in its annual report or in the report required under subsection (a) if appropriate) the results of any examination under the preceding sentence.
For purposes of this section, the term “incremental cost of alternative electric energy” means, with respect to electric energy purchased from a qualifying cogenerator or qualifying small power producer, the cost to the electric utility of the electric energy which, but for the purchase from such cogenerator or small power producer, such utility would generate or purchase from another source.
No contract between a Federal agency and any electric utility for the sale of electric energy by such Federal agency for resale which is entered into after November 9, 1978, may contain any provision which will have the effect of preventing the implementation of any rule under this section with respect to such utility. Any provision in any such contract which has such effect shall be null and void.
At the time of issuance of the license or exemption for the project, the Commission finds that the project will not have substantial adverse effects on the environment, including recreation and water quality. Such finding shall be made by the Commission after taking into consideration terms and conditions imposed under either paragraph (3) of this subsection or section 10 of the Federal Power Act [16 U.S.C. 803] (whichever is appropriate as required by that Act [16 U.S.C. 791a et seq.] or the Electric Consumers Protection Act of 1986) and compliance with other environmental requirements applicable to the project.
The project meets the terms and conditions set by fish and wildlife agencies under the same procedures as provided for under section 30(c) of the Federal Power Act [16 U.S.C. 823a(c)].
For purposes of this section, the term “new dam or diversion” means a dam or diversion which requires, for purposes of installing any hydroelectric power project, any construction, or enlargement of any impoundment or diversion structure (other than repairs or reconstruction or the addition of flashboards or similar adjustable devices) 3
For purposes of this section, the terms “small power production facility”, “qualifying small power production facility”, “qualifying small power producer”, “primary energy source”, “cogeneration facility”, “qualifying cogeneration facility”, and “qualifying cogenerator” have the respective meanings provided for such terms under section 3(17) and (18) of the Federal Power Act [16 U.S.C. 796(17), (18)].
Any electric utility may file an application with the Commission for relief from the mandatory purchase obligation pursuant to this subsection on a service territory-wide basis. Such application shall set forth the factual basis upon which relief is requested and describe why the conditions set forth in subparagraph (A), (B), or (C) of paragraph (1) of this subsection have been met. After notice, including sufficient notice to potentially affected qualifying cogeneration facilities and qualifying small power production facilities, and an opportunity for comment, the Commission shall make a final determination within 90 days of such application regarding whether the conditions set forth in subparagraph (A), (B), or (C) of paragraph (1) have been met.
At any time after the Commission makes a finding under paragraph (3) relieving an electric utility of its obligation to purchase electric energy, a qualifying cogeneration facility, a qualifying small power production facility, a State agency, or any other affected person may apply to the Commission for an order reinstating the electric utility’s obligation to purchase electric energy under this section. Such application shall set forth the factual basis upon which the application is based and describe why the conditions set forth in subparagraph (A), (B), or (C) of paragraph (1) of this subsection are no longer met. After notice, including sufficient notice to potentially affected utilities, and opportunity for comment, the Commission shall issue an order within 90 days of such application reinstating the electric utility’s obligation to purchase electric energy under this section if the Commission finds that the conditions set forth in subparagraphs (A), (B) or (C) of paragraph (1) which relieved the obligation to purchase, are no longer met.
Nothing in this subsection affects the rights or remedies of any party under any contract or obligation, in effect or pending approval before the appropriate State regulatory authority or non-regulated electric utility on August 8, 2005, to purchase electric energy or capacity from or to sell electric energy or capacity to a qualifying cogeneration facility or qualifying small power production facility under this Act (including the right to recover costs of purchasing electric energy or capacity).
Notwithstanding any transfer of functions under the first sentence of section 301(b) of the Department of Energy Organization Act [42 U.S.C. 7151(b)], no permit referred to in subsection (a)(1)(B) may be issued unless the Commission has conducted hearings and made the findings required under section 202(e) of the Federal Power Act [16 U.S.C. 824a(e)] and under the applicable execution order respecting the construction, operation, maintenance, or connection at the borders of the United States of facilities for the transmission of electric energy between the United States and a foreign country. Any finding of the Commission under an applicable executive order referred to in this subsection shall be treated for purposes of judicial review as an order issued under section 202(e) of the Federal Power Act.
The Secretary may not acquire any rights-of-day 2
This section shall not affect any Federal law governing Federal lands.
The Commission may grant any application for an order under this section in whole or in part and upon such terms and conditions as it finds necessary or appropriate to secure the maintenance of adequate service and the coordination in the public interest of facilities subject to the jurisdiction of the Commission. The Commission may from time to time for good cause shown make such orders supplemental to any order made under this section as it may find necessary or appropriate.
No public utility shall issue any security, or assume any obligation or liability as guarantor, indorser, surety, or otherwise in respect of any security of another person, unless and until, and then only to the extent that, upon application by the public utility, the Commission by order authorizes such issue or assumption of liability. The Commission shall make such order only if it finds that such issue or assumption (a) is for some lawful object, within the corporate purposes of the applicant and compatible with the public interest, which is necessary or appropriate for or consistent with the proper performance by the applicant of service as a public utility and which will not impair its ability to perform that service, and (b) is reasonably necessary or appropriate for such purposes. The provisions of this section shall be effective six months after August 26, 1935.
The Commission, after opportunity for hearing, may grant any application under this section in whole or in part, and with such modifications and upon such terms and conditions as it may find necessary or appropriate, and may from time to time, after opportunity for hearing and for good cause shown, make such supplemental orders in the premises as it may find necessary or appropriate, and may by any such supplemental order modify the provisions of any previous order as to the particular purposes, uses, and extent to which, or the conditions under which, any security so theretofore authorized or the proceeds thereof may be applied, subject always to the requirements of subsection (a) of this section.
No public utility shall, without the consent of the Commission, apply any security or any proceeds thereof to any purpose not specified in the Commission’s order, or supplemental order, or to any purpose in excess of the amount allowed for such purpose in such order, or otherwise in contravention of such order.
The Commission shall not authorize the capitalization of the right to be a corporation or of any franchise, permit, or contract for consolidation, merger, or lease in excess of the amount (exclusive of any tax or annual charge) actually paid as the consideration for such right, franchise, permit, or contract.
Subsection (a) shall not apply to the issue or renewal of, or assumption of liability on, a note or draft maturing not more than one year after the date of such issue, renewal, or assumption of liability, and aggregating (together with all other then outstanding notes and drafts of a maturity of one year or less on which such public utility is primarily or secondarily liable) not more than 5 per centum of the par value of the other securities of the public utility then outstanding. In the case of securities having no par value, the par value for the purpose of this subsection shall be the fair market value as of the date of issue. Within ten days after any such issue, renewal, or assumption of liability, the public utility shall file with the Commission a certificate of notification, in such form as may be prescribed by the Commission, setting forth such matters as the Commission shall by regulation require.
The provisions of this section shall not extend to a public utility organized and operating in a State under the laws of which its security issues are regulated by a State commission.
Nothing in this section shall be construed to imply any guarantee or obligation on the part of the United States in respect of any securities to which the provisions of this section relate.
Any public utility whose security issues are approved by the Commission under this section may file with the Securities and Exchange Commission duplicate copies of reports filed with the Federal Power Commission in lieu of the reports, information, and documents required under sections 77g, 78l, and 78m of title 15.
All rates and charges made, demanded, or received by any public utility for or in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable, and any such rate or charge that is not just and reasonable is hereby declared to be unlawful.
No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.
Under such rules and regulations as the Commission may prescribe, every public utility shall file with the Commission, within such time and in such form as the Commission may designate, and shall keep open in convenient form and place for public inspection schedules showing all rates and charges for any transmission or sale subject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services.
Unless the Commission otherwise orders, no change shall be made by any public utility in any such rate, charge, classification, or service, or in any rule, regulation, or contract relating thereto, except after sixty days’ notice to the Commission and to the public. Such notice shall be given by filing with the Commission and keeping open for public inspection new schedules stating plainly the change or changes to be made in the schedule or schedules then in force and the time when the change or changes will go into effect. The Commission, for good cause shown, may allow changes to take effect without requiring the sixty days’ notice herein provided for by an order specifying the changes so to be made and the time when they shall take effect and the manner in which they shall be filed and published.
Whenever any such new schedule is filed the Commission shall have authority, either upon complaint or upon its own initiative without complaint, at once, and, if it so orders, without answer or formal pleading by the public utility, but upon reasonable notice, to enter upon a hearing concerning the lawfulness of such rate, charge, classification, or service; and, pending such hearing and the decision thereon, the Commission, upon filing with such schedules and delivering to the public utility affected thereby a statement in writing of its reasons for such suspension, may suspend the operation of such schedule and defer the use of such rate, charge, classification, or service, but not for a longer period than five months beyond the time when it would otherwise go into effect; and after full hearings, either completed before or after the rate, charge, classification, or service goes into effect, the Commission may make such orders with reference thereto as would be proper in a proceeding initiated after it had become effective. If the proceeding has not been concluded and an order made at the expiration of such five months, the proposed change of rate, charge, classification, or service shall go into effect at the end of such period, but in case of a proposed increased rate or charge, the Commission may by order require the interested public utility or public utilities to keep accurate account in detail of all amounts received by reason of such increase, specifying by whom and in whose behalf such amounts are paid, and upon completion of the hearing and decision may by further order require such public utility or public utilities to refund, with interest, to the persons in whose behalf such amounts were paid, such portion of such increased rates or charges as by its decision shall be found not justified. At any hearing involving a rate or charge sought to be increased, the burden of proof to show that the increased rate or charge is just and reasonable shall be upon the public utility, and the Commission shall give to the hearing and decision of such questions preference over other questions pending before it and decide the same as speedily as possible.
If, pursuant to this subsection, a person seeks a rehearing under section 825l(a) of this title, and the Commission fails to act on the merits of the rehearing request by the date that is 30 days after the date of the rehearing request because the Commissioners are divided two against two, as a result of vacancy, incapacity, or recusal on the Commission, or if the Commission lacks a quorum, such person may appeal under section 825l(b) of this title.
Whenever the Commission, after a hearing held upon its own motion or upon complaint, shall find that any rate, charge, or classification, demanded, observed, charged, or collected by any public utility for any transmission or sale subject to the jurisdiction of the Commission, or that any rule, regulation, practice, or contract affecting such rate, charge, or classification is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate, charge, classification, rule, regulation, practice, or contract to be thereafter observed and in force, and shall fix the same by order. Any complaint or motion of the Commission to initiate a proceeding under this section shall state the change or changes to be made in the rate, charge, classification, rule, regulation, practice, or contract then in force, and the reasons for any proposed change or changes therein. If, after review of any motion or complaint and answer, the Commission shall decide to hold a hearing, it shall fix by order the time and place of such hearing and shall specify the issues to be adjudicated.
Whenever the Commission institutes a proceeding under this section, the Commission shall establish a refund effective date. In the case of a proceeding instituted on complaint, the refund effective date shall not be earlier than the date of the filing of such complaint nor later than 5 months after the filing of such complaint. In the case of a proceeding instituted by the Commission on its own motion, the refund effective date shall not be earlier than the date of the publication by the Commission of notice of its intention to initiate such proceeding nor later than 5 months after the publication date. Upon institution of a proceeding under this section, the Commission shall give to the decision of such proceeding the same preference as provided under section 824d of this title and otherwise act as speedily as possible. If no final decision is rendered by the conclusion of the 180-day period commencing upon initiation of a proceeding pursuant to this section, the Commission shall state the reasons why it has failed to do so and shall state its best estimate as to when it reasonably expects to make such decision. In any proceeding under this section, the burden of proof to show that any rate, charge, classification, rule, regulation, practice, or contract is unjust, unreasonable, unduly discriminatory, or preferential shall be upon the Commission or the complainant. At the conclusion of any proceeding under this section, the Commission may order refunds of any amounts paid, for the period subsequent to the refund effective date through a date fifteen months after such refund effective date, in excess of those which would have been paid under the just and reasonable rate, charge, classification, rule, regulation, practice, or contract which the Commission orders to be thereafter observed and in force: Provided, That if the proceeding is not concluded within fifteen months after the refund effective date and if the Commission determines at the conclusion of the proceeding that the proceeding was not resolved within the fifteen-month period primarily because of dilatory behavior by the public utility, the Commission may order refunds of any or all amounts paid for the period subsequent to the refund effective date and prior to the conclusion of the proceeding. The refunds shall be made, with interest, to those persons who have paid those rates or charges which are the subject of the proceeding.
Notwithstanding subsection (b), in a proceeding commenced under this section involving two or more electric utility companies of a registered holding company, refunds which might otherwise be payable under subsection (b) shall not be ordered to the extent that such refunds would result from any portion of a Commission order that (1) requires a decrease in system production or transmission costs to be paid by one or more of such electric companies; and (2) is based upon a determination that the amount of such decrease should be paid through an increase in the costs to be paid by other electric utility companies of such registered holding company: Provided, That refunds, in whole or in part, may be ordered by the Commission if it determines that the registered holding company would not experience any reduction in revenues which results from an inability of an electric utility company of the holding company to recover such increase in costs for the period between the refund effective date and the effective date of the Commission’s order. For purposes of this subsection, the terms “electric utility companies” and “registered holding company” shall have the same meanings as provided in the Public Utility Holding Company Act of 1935, as amended.1
The Commission upon its own motion, or upon the request of any State commission whenever it can do so without prejudice to the efficient and proper conduct of its affairs, may investigate and determine the cost of the production or transmission of electric energy by means of facilities under the jurisdiction of the Commission in cases where the Commission has no authority to establish a rate governing the sale of such energy.
Whenever the Commission, upon complaint of a State commission, after notice to each State commission and public utility affected and after opportunity for hearing, shall find that any interstate service of any public utility is inadequate or insufficient, the Commission shall determine the proper, adequate, or sufficient service to be furnished, and shall fix the same by its order, rule, or regulation: Provided, That the Commission shall have no authority to compel the enlargement of generating facilities for such purposes, nor to compel the public utility to sell or exchange energy when to do so would impair its ability to render adequate service to its customers.
The Commission may investigate and ascertain the actual legitimate cost of the property of every public utility, the depreciation therein, and, when found necessary for rate-making purposes, other facts which bear on the determination of such cost or depreciation, and the fair value of such property.
Every public utility upon request shall file with the Commission an inventory of all or any part of its property and a statement of the original cost thereof, and shall keep the Commission informed regarding the cost of all additions, betterments, extensions, and new construction.
The Commission may refer any matter arising in the administration of this subchapter to a board to be composed of a member or members, as determined by the Commission, from the State or each of the States affected or to be affected by such matter. Any such board shall be vested with the same power and be subject to the same duties and liabilities as in the case of a member of the Commission when designated by the Commission to hold any hearings. The action of such board shall have such force and effect and its proceedings shall be conducted in such manner as the Commission shall by regulations prescribe. The board shall be appointed by the Commission from persons nominated by the State commission of each State affected or by the Governor of such State if there is no State commission. Each State affected shall be entitled to the same number of representatives on the board unless the nominating power of such State waives such right. The Commission shall have discretion to reject the nominee from any State, but shall thereupon invite a new nomination from that State. The members of a board shall receive such allowances for expenses as the Commission shall provide. The Commission may, when in its discretion sufficient reason exists therefor, revoke any reference to such a board.
The Commission may confer with any State commission regarding the relationship between rate structures, costs, accounts, charges, practices, classifications, and regulations of public utilities subject to the jurisdiction of such State commission and of the Commission; and the Commission is authorized, under such rules and regulations as it shall prescribe, to hold joint hearings with any State commission in connection with any matter with respect to which the Commission is authorized to act. The Commission is authorized in the administration of this chapter to avail itself of such cooperation, services, records, and facilities as may be afforded by any State commission.
The Commission shall make available to the several State commissions such information and reports as may be of assistance in State regulation of public utilities. Whenever the Commission can do so without prejudice to the efficient and proper conduct of its affairs, it may upon request from a State make available to such State as witnesses any of its trained rate, valuation, or other experts, subject to reimbursement to the Commission by such State of the compensation and traveling expenses of such witnesses. All sums collected hereunder shall be credited to the appropriation from which the amounts were expended in carrying out the provisions of this subsection.
The Commission may, on its own motion, after compliance with the requirements of paragraphs (1) and (2) of subsection (b), issue an order requiring any action described in subsection (a)(1) if the Commission determines that such order meets the requirements of subsection (c). No such order may be issued upon the Commission’s own motion with respect to a Federal power marketing agency.
Any electric utility, Federal power marketing agency, or any other person generating electric energy for sale for resale, may apply to the Commission for an order under this subsection requiring a transmitting utility to provide transmission services (including any enlargement of transmission capacity necessary to provide such services) to the applicant. Upon receipt of such application, after public notice and notice to each affected State regulatory authority, each affected electric utility, and each affected Federal power marketing agency, and after affording an opportunity for an evidentiary hearing, the Commission may issue such order if it finds that such order meets the requirements of section 824k of this title, and would otherwise be in the public interest. No order may be issued under this subsection unless the applicant has made a request for transmission services to the transmitting utility that would be the subject of such order at least 60 days prior to its filing of an application for such order.
No order may be issued under this section or section 824i of this title if, after giving consideration to consistently applied regional or national reliability standards, guidelines, or criteria, the Commission finds that such order would unreasonably impair the continued reliability of electric systems affected by the order.
As used in this section, the term “facilities” means only facilities used for the generation or transmission of electric energy.
The requirements of subsection (b) shall not apply to facilities used in local distribution.
If the Commission, after an evidentiary hearing held on a complaint and after giving consideration to reliability standards established under section 824o of this title, finds on the basis of a preponderance of the evidence that any exemption granted pursuant to subsection (c) unreasonably impairs the continued reliability of an interconnected transmission system, the Commission shall revoke the exemption granted to the transmitting utility.
The rate changing procedures applicable to public utilities under subsections (c) and (d) of section 824d of this title are applicable to unregulated transmitting utilities for purposes of this section.
In exercising authority under subsection (b)(1), the Commission may remand transmission rates to an unregulated transmitting utility for review and revision if necessary to meet the requirements of subsection (b).
The provision of transmission services under subsection (b) does not preclude a request for transmission services under section 824j of this title.
The Commission may not require a State or municipality to take action under this section that would violate a private activity bond rule for purposes of section 141 of title 26.
Nothing in this section authorizes the Commission to require an unregulated transmitting utility to transfer control or operational control of its transmitting facilities to a Transmission Organization that is designated to provide nondiscriminatory transmission access.
An order under section 824j of this title shall require the transmitting utility subject to the order to provide wholesale transmission services at rates, charges, terms, and conditions which permit the recovery by such utility of all the costs incurred in connection with the transmission services and necessary associated services, including, but not limited to, an appropriate share, if any, of legitimate, verifiable and economic costs, including taking into account any benefits to the transmission system of providing the transmission service, and the costs of any enlargement of transmission facilities. Such rates, charges, terms, and conditions shall promote the economically efficient transmission and generation of electricity and shall be just and reasonable, and not unduly discriminatory or preferential. Rates, charges, terms, and conditions for transmission services provided pursuant to an order under section 824j of this title shall ensure that, to the extent practicable, costs incurred in providing the wholesale transmission services, and properly allocable to the provision of such services, are recovered from the applicant for such order and not from a transmitting utility’s existing wholesale, retail, and transmission customers.
If the Commission does not issue any order applied for under section 824i or 824j of this title, the Commission shall, by order, deny such application and state the reasons for such denial.
No order may be issued under this chapter which is inconsistent with any State law which governs the retail marketing areas of electric utilities.
With respect to an electric utility which is prohibited by Federal law from being a source of power supply, either directly or through a distributor of its electric energy, outside an area set forth in such law, no order issued under section 824j of this title may require such electric utility (or a distributor of such electric utility) to provide transmission services to another entity if the electric energy to be transmitted will be consumed within the area set forth in such Federal law, unless the order is in furtherance of a sale of electric energy to that electric utility: Provided, however, That the foregoing provision shall not apply to any area served at retail by an electric transmission system which was such a distributor on October 24, 1992, and which before October 1, 1991, gave its notice of termination under its power supply contract with such electric utility.
Any order under section 824j of this title requiring provision of transmission services in whole or in part within ERCOT shall provide that any ERCOT utility which is not a public utility and the transmission facilities of which are actually used for such transmission service is entitled to receive compensation based, insofar as practicable and consistent with subsection (a), on the transmission ratemaking methodology used by the Public Utility Commission of Texas.
Whenever any electric utility, Federal power marketing agency, or any other person generating electric energy for sale for resale makes a good faith request to a transmitting utility to provide wholesale transmission services and requests specific rates and charges, and other terms and conditions, unless the transmitting utility agrees to provide such services at rates, charges, terms and conditions acceptable to such person, the transmitting utility shall, within 60 days of its receipt of the request, or other mutually agreed upon period, provide such person with a detailed written explanation, with specific reference to the facts and circumstances of the request, stating (1) the transmitting utility’s basis for the proposed rates, charges, terms, and conditions for such services, and (2) its analysis of any physical or other constraints affecting the provision of such services.
Not later than 1 year after October 24, 1992, the Commission shall promulgate a rule requiring that information be submitted annually to the Commission by transmitting utilities which is adequate to inform potential transmission customers, State regulatory authorities, and the public of potentially available transmission capacity and known constraints.
No rate or charge received by an exempt wholesale generator for the sale of electric energy shall be lawful under section 824d of this title if, after notice and opportunity for hearing, the Commission finds that such rate or charge results from the receipt of any undue preference or advantage from an electric utility which is an associate company or an affiliate of the exempt wholesale generator. For purposes of this section, the terms “associate company” and “affiliate” shall have the same meaning as provided in section 16451 of title 42.1
The Electric Reliability Organization shall file with the Commission for approval any proposed rule or proposed rule change, accompanied by an explanation of its basis and purpose. The Commission, upon its own motion or complaint, may propose a change to the rules of the ERO. A proposed rule or proposed rule change shall take effect upon a finding by the Commission, after notice and opportunity for comment, that the change is just, reasonable, not unduly discriminatory or preferential, is in the public interest, and satisfies the requirements of subsection (c).
The ERO shall conduct periodic assessments of the reliability and adequacy of the bulk-power system in North America.
The President is urged to negotiate international agreements with the governments of Canada and Mexico to provide for effective compliance with reliability standards and the effectiveness of the ERO in the United States and Canada or Mexico.
The Commission shall establish a regional advisory body on the petition of at least two-thirds of the States within a region that have more than one-half of their electric load served within the region. A regional advisory body shall be composed of one member from each participating State in the region, appointed by the Governor of each State, and may include representatives of agencies, States, and provinces outside the United States. A regional advisory body may provide advice to the Electric Reliability Organization, a regional entity, or the Commission regarding the governance of an existing or proposed regional entity within the same region, whether a standard proposed to apply within the region is just, reasonable, not unduly discriminatory or preferential, and in the public interest, whether fees proposed to be assessed within the region are just, reasonable, not unduly discriminatory or preferential, and in the public interest and any other responsibilities requested by the Commission. The Commission may give deference to the advice of any such regional advisory body if that body is organized on an Interconnection-wide basis.
The provisions of this section do not apply to Alaska or Hawaii.
The terms “bulk-power system”, “Electric Reliability Organization”, and “regional entity” have the meanings given such terms in paragraphs (1), (2), and (7) of section 824o(a) of this title, respectively.
The term “critical electric infrastructure” means a system or asset of the bulk-power system, whether physical or virtual, the incapacity or destruction of which would negatively affect national security, economic security, public health or safety, or any combination of such matters.
The term “critical electric infrastructure information” means information related to critical electric infrastructure, or proposed critical electrical infrastructure, generated by or provided to the Commission or other Federal agency, other than classified national security information, that is designated as critical electric infrastructure information by the Commission or the Secretary pursuant to subsection (d). Such term includes information that qualifies as critical energy infrastructure information under the Commission’s regulations.
The term “defense critical electric infrastructure” means any electric infrastructure located in any of the 48 contiguous States or the District of Columbia that serves a facility designated by the Secretary pursuant to subsection (c), but is not owned or operated by the owner or operator of such facility.
The term “electromagnetic pulse” means 1 or more pulses of electromagnetic energy emitted by a device capable of disabling or disrupting operation of, or destroying, electronic devices or communications networks, including hardware, software, and data, by means of such a pulse.
The term “geomagnetic storm” means a temporary disturbance of the Earth’s magnetic field resulting from solar activity.
The term “Secretary” means the Secretary of Energy.
Whenever the President issues and provides to the Secretary a written directive or determination identifying a grid security emergency, the Secretary may, with or without notice, hearing, or report, issue such orders for emergency measures as are necessary in the judgment of the Secretary to protect or restore the reliability of critical electric infrastructure or of defense critical electric infrastructure during such emergency. As soon as practicable but not later than 180 days after December 4, 2015, the Secretary shall, after notice and opportunity for comment, establish rules of procedure that ensure that such authority can be exercised expeditiously.
Whenever the President issues and provides to the Secretary a written directive or determination under paragraph (1), the President shall promptly notify congressional committees of relevant jurisdiction, including the Committee on Energy and Commerce of the House of Representatives and the Committee on Energy and Natural Resources of the Senate, of the contents of, and justification for, such directive or determination.
Before issuing an order for emergency measures under paragraph (1), the Secretary shall, to the extent practicable in light of the nature of the grid security emergency and the urgency of the need for action, consult with appropriate governmental authorities in Canada and Mexico, entities described in paragraph (4), the Electricity Sub-sector Coordinating Council, the Commission, and other appropriate Federal agencies regarding implementation of such emergency measures.
Except as provided in subparagraph (B), an order for emergency measures issued under paragraph (1) shall expire no later than 15 days after its issuance.
The Secretary may reissue an order for emergency measures issued under paragraph (1) for subsequent periods, not to exceed 15 days for each such period, provided that the President, for each such period, issues and provides to the Secretary a written directive or determination that the grid security emergency identified under paragraph (1) continues to exist or that the emergency measure continues to be required.
If the Commission determines that owners, operators, or users of critical electric infrastructure have incurred substantial costs to comply with an order for emergency measures issued under this subsection and that such costs were prudently incurred and cannot reasonably be recovered through regulated rates or market prices for the electric energy or services sold by such owners, operators, or users, the Commission shall, consistent with the requirements of section 824d of this title, after notice and an opportunity for comment, establish a mechanism that permits such owners, operators, or users to recover such costs.
To the extent the owner or operator of defense critical electric infrastructure is required to take emergency measures pursuant to an order issued under this subsection, the owners or operators of a critical defense facility or facilities designated by the Secretary pursuant to subsection (c) that rely upon such infrastructure shall bear the full incremental costs of the measures.
The Secretary, and other appropriate Federal agencies, shall, to the extent practicable and consistent with their obligations to protect classified information, provide temporary access to classified information related to a grid security emergency for which emergency measures are issued under paragraph (1) to key personnel of any entity subject to such emergency measures to enable optimum communication between the entity and the Secretary and other appropriate Federal agencies regarding the grid security emergency.
Information may be designated by the Commission or the Secretary as critical electric infrastructure information pursuant to the criteria and procedures established by the Commission under paragraph (2)(A).
In exercising their respective authorities under this subsection, the Commission and the Secretary shall take into consideration the role of State commissions in reviewing the prudence and cost of investments, determining the rates and terms of conditions for electric services, and ensuring the safety and reliability of the bulk-power system and distribution facilities within their respective jurisdictions.
The Commission and the Secretary shall, in consultation with Canadian and Mexican authorities, develop protocols for the voluntary sharing of critical electric infrastructure information with Canadian and Mexican authorities and owners, operators, and users of the bulk-power system outside the United States.
Nothing in this section shall require a person or entity in possession of critical electric infrastructure information to share such information with Federal, State, political subdivision, or tribal authorities, or any other person or entity.
Nothing in this section shall permit or authorize the withholding of information from Congress, any committee or subcommittee thereof, or the Comptroller General.
In implementing this section, the Commission and the Secretary shall segregate critical electric infrastructure information or information that reasonably could be expected to lead to the disclosure of the critical electric infrastructure information within documents and electronic communications, wherever feasible, to facilitate disclosure of information that is not designated as critical electric infrastructure information.
Information may not be designated as critical electric infrastructure information for longer than 5 years, unless specifically re-designated by the Commission or the Secretary, as appropriate.
The Commission or the Secretary, as appropriate, shall remove the designation of critical electric infrastructure information, in whole or in part, from a document or electronic communication if the Commission or the Secretary, as appropriate, determines that the unauthorized disclosure of such information could no longer be used to impair the security or reliability of the bulk-power system or distribution facilities.
Notwithstanding section 825l(b) of this title, with respect to a petition filed by a person to which an order under this section applies, any determination by the Commission or the Secretary concerning the designation of critical electric infrastructure information under this subsection shall be subject to review under chapter 7 of title 5, except that such review shall be brought in the district court of the United States in the district in which the complainant resides, or has his principal place of business, or in the District of Columbia. In such a case the court shall examine in camera the contents of documents or electronic communications that are the subject of the determination under review to determine whether such documents or any part thereof were improperly designated or not designated as critical electric infrastructure information.
The Secretary shall facilitate and, to the extent practicable, expedite the acquisition of adequate security clearances by key personnel of any entity subject to the requirements of this section, to enable optimum communication with Federal agencies regarding threats to the security of the critical electric infrastructure. The Secretary, the Commission, and other appropriate Federal agencies shall, to the extent practicable and consistent with their obligations to protect classified and critical electric infrastructure information, share timely actionable information regarding grid security with appropriate key personnel of owners, operators, and users of the critical electric infrastructure.
Except as provided in paragraph (4), to the extent any action or omission taken by an entity that is necessary to comply with an order for emergency measures issued under subsection (b)(1), including any action or omission taken to voluntarily comply with such order, results in noncompliance with, or causes such entity not to comply with any rule, order, regulation, or provision of this chapter, including any reliability standard approved by the Commission pursuant to section 824o of this title, such action or omission shall not be considered a violation of such rule, order, regulation, or provision.
Except as provided in paragraph (4), an action or omission taken by an owner, operator, or user of critical electric infrastructure or of defense critical electric infrastructure to comply with an order for emergency measures issued under subsection (b)(1) shall be treated as an action or omission taken to comply with an order issued under section 824a(c) of this title for purposes of such section.
No cause of action shall lie or be maintained in any Federal or State court for the sharing or receipt of information under, and that is conducted in accordance with, subsection (d).
Nothing in this subsection shall be construed to require dismissal of a cause of action against an entity that, in the course of complying with an order for emergency measures issued under subsection (b)(1) by taking an action or omission for which they would be liable but for paragraph (1) or (2), takes such action or omission in a grossly negligent manner.
In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.
Nothing in this section precludes any person from constructing or modifying any transmission facility in accordance with State law.
This section shall not apply within the area referred to in section 824k(k)(2)(A) of this title.
Nothing in subsections (b)(1), (b)(2), and (b)(3) of this section shall affect any existing or future methodology employed by a Transmission Organization for allocating or auctioning transmission rights if such Transmission Organization was authorized by the Commission to allocate or auction financial transmission rights on its system as of January 1, 2005, and the Commission determines that any future allocation or auction is just, reasonable and not unduly discriminatory or preferential, provided, however, that if such a Transmission Organization never allocated financial transmission rights on its system that pertained to a period before January 1, 2005, with respect to any application by such Transmission Organization that would change its methodology the Commission shall exercise its authority in a manner consistent with the 1
The Commission may exercise authority under this chapter to make transmission rights not used to meet an obligation covered by subsection (b) available to other entities in a manner determined by the Commission to be just, reasonable, and not unduly discriminatory or preferential.
Nothing in this chapter relieves a load-serving entity from any obligation under State or local law to build transmission or distribution facilities adequate to meet the service obligations of the load-serving entity.
Nothing in this section shall provide a basis for abrogating any contract or service agreement for firm transmission service or rights in effect as of August 8, 2005. If an ISO in the Western Interconnection had allocated financial transmission rights prior to August 8, 2005, but had not done so with respect to one or more load-serving entities’ firm transmission rights held under contracts to which the preceding sentence applies (or held by reason of ownership or future ownership of transmission facilities), such load-serving entities may not be required, without their consent, to convert such firm transmission rights to tradable or financial rights, except where the load-serving entity has voluntarily joined the ISO as a participating transmission owner (or its successor) in accordance with the ISO tariff.
The Commission shall ensure that any entity described in section 824(f) of this title that owns transmission facilities used predominately to support its own water pumping facilities shall have, with respect to the facilities, protections for transmission service comparable to those provided to load-serving entities pursuant to this section.
This section shall not apply within the area referred to in section 824k(k)(2)(A) of this title.
This section does not authorize the Commission to take any action not otherwise within the jurisdiction of the Commission.
An entity that to the extent required to meet its service obligations exercises rights described in subsection (b) shall not be considered by such action as engaging in undue discrimination or preference under this chapter.
Not later than 1 year after August 8, 2005, the Commission shall establish, by rule, incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefitting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion.
In the rule issued under this section, the Commission shall, to the extent within its jurisdiction, provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization. The Commission shall ensure that any costs recoverable pursuant to this subsection may be recovered by such utility through the transmission rates charged by such utility or through the transmission rates charged by the Transmission Organization that provides transmission service to such utility.
All rates approved under the rules adopted pursuant to this section, including any revisions to the rules, are subject to the requirements of sections 824d and 824e of this title that all rates, charges, terms, and conditions be just and reasonable and not unduly discriminatory or preferential.
The term “advanced cybersecurity technology” means any technology, operational capability, or service, including computer hardware, software, or a related asset, that enhances the security posture of public utilities through improvements in the ability to protect against, detect, respond to, or recover from a cybersecurity threat (as defined in section 650 of title 6).
The term “advanced cybersecurity technology information” means information relating to advanced cybersecurity technology or proposed advanced cybersecurity technology that is generated by or provided to the Commission or another Federal agency.
Any rule issued pursuant to this section shall preclude rate treatments that allow unjust and unreasonable double recovery for advanced cybersecurity technology.
The Commission shall permit public utilities to apply for incentive-based rate treatment under a rule issued under this section on a single-issue basis by submitting to the Commission a tariff schedule under section 824d of this title that permits recovery of costs and incentives over the depreciable life of the applicable assets, without regard to changes in receipts or other costs of the public utility.
Advanced cybersecurity technology information that is provided to, generated by, or collected by the Federal Government under subsection (b), (c), or (f) shall be considered to be critical electric infrastructure information under section 824o–1 of this title.
The Commission shall not require entities who have a de minimis market presence to comply with the reporting requirements of this section.
This section shall not apply to a transaction for the purchase or sale of wholesale electric energy or transmission services within the area described in section 824k(k)(2)(A) of this title.
No entity (including an entity described in section 824(f) of this title) shall willfully and knowingly report any information relating to the price of electricity sold at wholesale or the availability of transmission capacity, which information the person or any other entity knew to be false at the time of the reporting, to a Federal agency with intent to fraudulently affect the data being compiled by the Federal agency.
It shall be unlawful for any entity (including an entity described in section 824(f) of this title), directly or indirectly, to use or employ, in connection with the purchase or sale of electric energy or the purchase or sale of transmission services subject to the jurisdiction of the Commission, any manipulative or deceptive device or contrivance (as those terms are used in section 78j(b) of title 15), in contravention of such rules and regulations as the Commission may prescribe as necessary or appropriate in the public interest or for the protection of electric ratepayers.
Nothing in this section shall be construed to create a private right of action.
The Commission shall convene joint boards on a regional basis pursuant to section 824h of this title to study the issue of security constrained economic dispatch for the various market regions. The Commission shall designate the appropriate regions to be covered by each such joint board for purposes of this section.
The Commission shall request each State to nominate a representative for the appropriate regional joint board, and shall designate a member of the Commission to chair and participate as a member of each such board.
The sole authority of each joint board convened under this section shall be to consider issues relevant to what constitutes “security constrained economic dispatch” and how such a mode of operating an electric energy system affects or enhances the reliability and affordability of service to customers in the region concerned and to make recommendations to the Commission regarding such issues.
Within 1 year after August 8, 2005, the Commission shall issue a report and submit such report to the Congress regarding the recommendations of the joint boards under this section and the Commission may consolidate the recommendations of more than one such regional joint board, including any consensus recommendations for statutory or regulatory reform.