Collapse to view only § 8321. Temporary exemptions

§ 8321. Temporary exemptions
(a) General exemption due to lack of alternate fuel supply, site limitations, or environmental requirements
After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption, despite diligent good faith efforts—
(1) it is likely that an adequate and reliable supply of coal or other alternate fuel of the quality necessary to conform with design and operational requirements for use as a primary energy source will not be available to such powerplant at a cost (taking into account associated facilities for the transportation and use of such fuel) which, based upon the best practicable estimates, does not substantially exceed the cost, as determined by rule by the Secretary, of the fuel that would be used as a primary energy source;
(2) one or more site limitations exist which would ot 1
1 So in original. Probably should be “not”.
permit the location or operation of such a powerplant using coal or any other alternate fuel as a primary energy source; or
(3) the prohibitions of section 8311 of this title could not be satisfied without violating applicable environmental requirements.
(b) Temporary exemption based upon future use of synthetic fuels
After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that—
(1) the petitioner will comply with the prohibitions of part A by the end of the proposed exemption by the use of a synthetic fuel derived from coal or another alternate fuel; and
(2) the petitioner is not able to comply with such prohibitions by the use of such synthetic fuel until the end of the proposed exemption.
The effectiveness of an exemption under this subsection is conditioned on the petitioner filing and maintaining a compliance plan meeting the requirements of section 8324(b) of this title.
(c), (d) Repealed. Pub. L. 100–42, § 1(c)(5)(E), May 21, 1987, 101 Stat. 312
(e) Duration of temporary exemptions
(1) Except as provided in paragraph (2), exemptions under this section for any powerplant may not exceed, taking into account any extension or renewal, 5 years.
(2)
(A) An exemption under subsection (a)(1) may be granted for a period of more than 5 years, but may not exceed, taking into account any extension or renewal, 10 years.
(B) An exemption under subsection (b) may be extended beyond the 5-year limit under paragraph (1), but such exemption, so extended, may not exceed 10 years.
(3) If an exemption is granted for any powerplant before the powerplant is placed in service, the period before it is placed in service shall not be taken into account in computing the 5-year and the 10-year limitations of paragraphs (1) and (2).
(Pub. L. 95–620, title II, § 211, Nov. 9, 1978, 92 Stat. 3299; Pub. L. 100–42, § 1(c)(5), May 21, 1987, 101 Stat. 312.)
§ 8322. Permanent exemptions
(a) Permanent exemption due to lack of alternate fuel supply, site limitations, environmental requirements, or adequate capital
(1) After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that despite diligent good faith efforts—
(A) it is likely that an adequate and reliable supply of coal or other alternate fuel of the quality necessary to conform with design and operational requirements for use as a primary energy source (i) will not be available within the first 10 years of the useful life of the powerplant, or (ii) will not be available at a cost (taking into account associated facilities for the transportation and use of such fuel) which, based upon the best practicable estimates, does not substantially exceed the cost, as determined by rule by the Secretary, of the fuel that would be used as a primary energy source during the useful life of the powerplant involved;
(B) one or more site limitations exist which would not permit the location or operation of such powerplant using coal or any other alternate fuel as a primary energy source;
(C) the prohibitions of part A could not be satisfied without violating applicable environmental requirements; or
(D) the required use of coal or any other alternate fuel would not allow the petitioner to obtain adequate capital for the financing of such powerplant.
(2) The demonstration required to be made by a petitioner under paragraph (1) shall be made with respect to the site of such powerplant and reasonable alternative sites.
(b) Permanent exemption due to certain State or local requirementsAfter consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary may, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that—
(1) with respect to the proposed site of the powerplant, the construction or operation of such a facility using coal or any other alternate fuel is infeasible because of a State or local requirement (other than a building code or a nuisance or zoning law);
(2) there is no reasonable alternative site for such powerplant which meets the criteria set forth in subsection (a)(1)(A) through (D); and
(3) the granting of the exemption would be in the public interest and would be consistent with the purposes of this chapter.
(c) Permanent exemption for cogenerationAfter consideration of a petition (and comments thereon) for an exemption from one or more of the prohibitions of part A for a cogeneration facility, the Secretary may, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he—
(1) finds that the petitioner has demonstrated that economic and other benefits of cogeneration are unobtainable unless petroleum or natural gas, or both, are used in such facility, and
(2) includes in the final order a statement of the basis for such finding.
(d) Permanent exemption for certain mixtures containing natural gas or petroleumAfter consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum, if he finds that the petitioner has demonstrated that—
(1) the powerplant uses, or proposes to use, a mixture of petroleum or natural gas and coal or another alternate fuel as a primary energy source; and
(2) the amount of the petroleum or natural gas used in such mixture will not exceed the minimum percentage of the total Btu heat input of the primary energy sources of such powerplant needed to maintain reliability of operation of such powerplant consistent with maintaining a reasonable level of fuel efficiency, as determined in accordance with rules prescribed by the Secretary.
(e) Permanent exemption for emergency purposes
(f) Permanent exemption for powerplants necessary to maintain reliability of serviceAfter consideration of a petition (and comments thereon) for an exemption for a powerplant from one or more of the prohibitions of part A, the Secretary may, by order, grant a permanent exemption under this subsection with respect to natural gas or petroleum if he finds that the petitioner has demonstrated that—
(1) such exemption is necessary to prevent impairment of reliability of service, and
(2) the petitioner, despite diligent good faith efforts, is not able to make the demonstration necessary to obtain an exemption under subsection (a) or (b) in the time required to prevent such impairment of service.
(Pub. L. 95–620, title II, § 212, Nov. 9, 1978, 92 Stat. 3300; Pub. L. 100–42, § 1(c)(6), May 21, 1987, 101 Stat. 312.)
§ 8323. General requirements for exemptions
(a) Use of mixtures or fluidized bed combustion not feasible
Except in the case of an exemption under section 8322(d) of this title, the Secretary may grant a permanent exemption for a powerplant under this part only—
(1) if the applicant has demonstrated that the use of a mixture of natural gas or petroleum and coal or another alternate fuel, for which an exemption under section 8322(d) of this title would be available, is not economically or technically feasible; and
(2) if the Secretary has not made a finding that the use of a method of fluidized bed combustion of coal or another alternate fuel is economically and technically feasible.
(b) State approval required for powerplant
(c) No alternative power supply in the case of a powerplant
(1) Except in the case of an exemption under section 8322(c) of this title, the Secretary may not grant an exemption for a new powerplant unless he finds that the petitioner has demonstrated that there is no alternative supply of electric power which is available within a reasonable distance at a reasonable cost without impairing short-run or long-run reliability of service and which can be obtained by the petitioner, despite reasonable good faith efforts.
(2) The Secretary shall forward a copy of any such petition to the Federal Energy Regulatory Commission promptly after it is filed with the Secretary and shall consult with such Commission before making any finding on such petition under paragraph (1).
(Pub. L. 95–620, title II, § 213, Nov. 9, 1978, 92 Stat. 3304; Pub. L. 100–42, § 1(c)(7), May 21, 1987, 101 Stat. 312.)
§ 8324. Terms and conditions; compliance plans
(a) Terms and conditions generally
(b) Compliance plans
A compliance plan meets the requirements of this subsection if it is approved by the Secretary and—
(1) contains (A) a schedule indicating how compliance with applicable prohibitions of this chapter will occur and (B) evidence of binding contracts for fuel, or facilities for the production of fuel, which would allow or 1
1 So in original. Probably should be “for”.
such compliance; and
(2) is revised at such times and to such extent as the Secretary may require to reflect changes in circumstances.
(Pub. L. 95–620, title II, § 214, Nov. 9, 1978, 92 Stat. 3304; Pub. L. 100–42, § 1(c)(8), May 21, 1987, 101 Stat. 312.)