Collapse to view only § 1919.32 - Specially designed blocks and components.

§ 1919.26 - Visual inspection before tests.

Before any test under this subpart E is carried out, a visual inspection of the gear involved shall be conducted and any visibly defective gear shall be replaced or repaired. The provisions of § 1919.15(d) shall be adhered to.

§ 1919.27 - Unit proof tests—winches, derricks and gear accessory thereto.

(a) Winches, with the whole of the gear accessory thereto (including derricks, goosenecks, eye plates, eye bolts, or other attachments), shall be tested with a proof load which shall exceed the safe working load as follows:

Safe working load Proof load Up to 20 tons25 percent in excess. 20-50 tons5 tons in excess. Over 50 tons10 percent in excess.

(b) The proof load shall be lifted with the vessel's normal tackle with the derrick at an angle not more than 15 degrees to the horizontal, or, at the designed minimum angle when this is greater, or, when this is impracticable, at the lowest practicable angle. The angle at which the test was made shall be stated in the certificate of test. After the proof load has been lifted, it shall be swung as far as possible in both directions. In applying the proof load, the design factors of the gear concerned will determine whether the load is applied with a single part fall or with a purchase and the certificate of test shall state the means used. Where winches are fitted with mechanical brakes for manual operation they shall be demonstrated to be in satisfactory operating condition.

(c) In the case of heavy lift derrick barges, proof loads shall be applied, except as limited by design and stability considerations, at the maximum and minimum radii for which designed, as well as at any intermediate radius which the surveyor may deem necessary, and shall be swung as far as possible in both directions. Data with respect to each proof load applied shall be entered in the test certificate.

(d) No items of cargo gear furnished by outside sources shall be used as a part of the vessel's gear for the purpose of accomplishing the proof test.

(e) All tests prescribed by this section should in general be carried out by dead load, except that in the case of quadrennial tests, replacements, or renewals, spring or hydraulic balances may be used where dead loads are not reasonably available. However, no exception shall be allowed in the case of gear on new vessels.

(f) The test shall not be regarded as satisfactory unless the indicator remains constant under the proof load for a period of at least 5 minutes.

(g)(1) The safe working load, determined pursuant to the requirements of this section, shall be applicable only to a swinging derrick. When using two fixed derricks in “union purchase” rigs, the safe working load should generally be reduced. It is recommended that owners obtain union purchase safe working load certification based upon design study and analysis by, or acceptable to, a qualified technical office of an accredited gear certification agency, with the recognition that such determinations are valid only for the conditions contemplated in the analysis.

(2) Where both guys and preventers are fitted, union purchase certification shall state whether the guy or the preventer is the working strength member, when the guy is for slewing only, and when the guy and preventer should share working loads as far as practicable.

(h) When necessary in the proof testing of heavy derricks, the appropriate shrouds and stays shall be rigged.

§ 1919.28 - Unit proof tests—cranes and gear accessory thereto.

(a) Except as noted in paragraph (e) of this section, cranes and other hoisting machines, together with gear accessory thereto, shall be tested with a proof load which shall exceed the safe working load as follows:

Safe working load Proof load Up to 20 tons25 percent in excess. 20-50 tons5 tons in excess. Over 50 tons10 percent in excess.

(b) The proof load shall be lifted and swung as far as possible in both directions. If the jib or boom of the crane has a variable radius, it shall be tested with proof loads, as specified in paragraph (a) of this section, at the maximum and minimum radii. In the case of hydraulic cranes, when due to the limitation of pressure it is impossible to lift a load 25 percent in excess of the safe working load, it will be sufficient to lift the greatest possible load.

(c) Initial proof tests of new cranes shall be made only with a dead load as specified in paragraph (b) of this section.

(d) Initial tests of cranes which have been in service, quadrennial tests, or tests associated with replacements or renewals, may be made with spring or hydraulic balances where dead loads are not reasonably available under the following conditions:

(1) Tests shall be conducted at maximum, minimum, and intermediate radius points, as well as such points in the arc of rotation as meet with the approval of the accredited person.

(2) An additional test shall be conducted with partial load and shall include all functions and movements contemplated in the use of the crane.

(e) In cases where shore-type cranes are mounted permanently aboard barges, the requirements of this Subpart E with respect to unit proof tests and examinations shall not apply and the applicable requirements of Subpart H of this part shall be adhered to with respect to unit proof tests and examinations.

§ 1919.29 - Limitations on safe working loads and proof loads.

The proof loads specified by §§ 1919.27 and 1919.28 shall be adjusted as necessary to meet any pertinent limitations based on stability and/or on structural competence at particular radii. Safe working loads shall be reduced accordingly.

§ 1919.30 - Examinations subsequent to unit tests.

(a) After satisfactory completion of the unit proof load tests required by §§ 1919.27 and 1919.28, the cargo gear and all component parts thereof shall be given a thorough visual examination, supplemented as necessary by other means, such as a hammer test or with electronic, ultrasonic, or other nondestructive methods, to determine if any of the parts were damaged, deformed, or otherwise rendered unsafe for further use.

(b) When the test of gear referred to in paragraph (a) of this section is being conducted for the first time on a vessel, accessory gear shall be dismantled or disassembled for examination after the test. The sheaves and pins of the blocks included in this test need not be removed unless there is evidence of deformation or failure.

(c) For subsequent tests such parts of the gear shall be dismantled or disassembled after the test as necessary to determine their suitability for continued service.

(d) When blocks are disassembled all shell bolt nuts shall be securely locked upon reassembly.

(e) In carrying out the requirements of this section, replacement shall be required of:

(1) Any swivel found to have excessive tolerance as a result of wear on any bearing surface.

(2) Pins of blocks found to be shouldered, notched, or grooved from wear, in which case, in addition to replacing the pin, sheave bushings shall be examined for suitability for continued use.

§ 1919.31 - Proof tests—loose gear.

(a) Chains, rings, shackles and other loose gear (whether accessory to a machine or not) shall be tested with a proof load against the article equal to that shown in the following table:

Article of gear Proof load Chain, ring, hook, shackle or swivel100 percent in excess of the safe working load. Blocks: Single sheave block300 percent in excess of the safe working load. 1Multiple sheave block with safe working load up to and including 20 tons100 percent in excess of the safe working load. Multiple sheave block with safe working load over 20 tons up to and including 40 tons20 tons in excess of the safe working load. Multiple sheave block with safe working load over 40 tons50 percent in excess of the safe working load. Pitched chains used with hand-operated blocks and rings, hooks, shackles or swivels permanently attached thereto50 percent in excess of the safe working load. Hand-operated blocks used with pitched chains and rings, hooks, shackles or swivels permanently attached thereto50 percent in excess of the safe working load.

1 The proof load applied to the block is equivalent to twice the maximum resultant load on the eye of pin of the block when lifting the nominal safe working load defined in (i) below. The proof load is, therefore, equal to four times the safe working load as defined in (i) below or twice the safe working load as defined in (ii) below.

(i) The nominal safe working load of a single-sheave block should be the maximum load which can be safely lifted by the block when the load is attached to a rope which passes around the sheave of the block.

(ii) In the case of a single-sheave block where the load is attached directly to the block instead of to a rope passing around the sheave, it is permissible to lift a load equal to twice the nominal safe working load of the block as defined in (i) above.

(iii) In the case of a lead block so situated that an acute angle cannot be formed by the two parts of the rope passing over it (i.e., the angle is always 90° or more), the block need not have a greater nominal safe working load than one-half the maximum resultant load which can be placed upon it.

(b) In cases where persons accredited to carry out loose gear tests may be retained to conduct tests of special stevedoring gear as described in § 1918.61(b) of this chapter, which does not form part of a vessel's equipment, such tests shall adhere to the requirements set forth in § 1918.61(b) (1), (2), and (3) of this chapter.

(c) After being tested as required by paragraph (a) of this section, and before being taken into use, all chains, rings, hooks, shackles, blocks or other loose gear, except as noted in § 1919.32, shall be thoroughly examined, the sheaves and pins of the blocks being removed for this purpose, to determine whether any part has been injured or permanently deformed by the test. Shell bolt nuts shall be securely locked upon reassembly. Defective loose gear components shall be replaced before the certificate is issued.

(d) Any certificate relating to shackles, swivels or strength members of single-sheave blocks which have been restored to original dimensions by welding shall state this fact.

§ 1919.32 - Specially designed blocks and components.

(a) Blocks and connecting components of an unusual nature which are specially designed and constructed as an integral part of a particular lifting unit and are either permanently affixed or of such design that two or more components must be tested together need not be considered as loose gear for purposes of § 1919.31.

(b) In lieu of the loose gear proof test required by § 1919.31(a), design data shall be submitted to an accredited certification agency indicating design and material specifications and analysis whereby the designed strength of such gear may be determined.

(c) Subsequent to the test of the lifting unit as a whole, a thorough visual examination shall be made of disassembled parts and an electronic, ultrasonic, or other equally efficient nondestructive examination shall be made of those parts not dismantled to ensure the safe condition of such parts.

§ 1919.33 - Proof tests—wire rope.

Wire rope, except as provided in § 1919.14(b), shall be tested by sample, a piece being tested to destruction, and the safe working load of running ropes, unless otherwise acceptable to the Administration on the basis of design, shall not exceed one-fifth of the breaking load of the sample tested. In the case of running ropes used in gear with a safe working load exceeding 10 tons, the safe working load shall not exceed one-fourth of the breaking load of the sample tested.

§ 1919.34 - Proof tests after repairs or alterations.

When proof loads are applied after repairs or alterations, all parts of the assembled gear shall be examined as required in §§ 1919.30, 1919.31(c), or 1919.32(c), whichever is applicable.

§ 1919.35 - Order of tests.

When both unit and loose gear proof load tests are required, the loose gear test may be carried out after completion of the unit test.

§ 1919.36 - Heat treatment.

(a) The annealing of wrought iron gear required by this part shall be accomplished at a temperature between 1100° and 1200 °F. and the exposure shall be of between 30 and 60 minutes duration. After being annealed, the gear shall be allowed to cool slowly and shall then be carefully inspected. All annealing shall be carried out in a closed furnace.

(b) When heat treatment of loose gear made of other than wrought iron or steel is recommended by the manufacturer, it shall be carried out in accordance with the specifications of the manufacturer.

§ 1919.37 - Competent persons.

All gear certification functions shall be performed by competent persons as set forth in the following table:

Functions Competent person Any testing, examination, inspection, or heat treatment required in United States portsResponsible individual, surveyor or other authorized agent of a person accredited by the Administration under the regulations contained in this part. Any testing, examination, inspection, or heat treatment required while the vessel is in other than United States portsResponsible individual, surveyor or other authorized agent of persons recognized by the Commandant of the United States Coast Guard or by a foreign nation whose certification is accepted by the Administration as being in substantial accordance with § 1918.12(a) of this chapter. Testing, examination and inspection of loose gear or wire rope; heat treatment of loose gearEmployees or authorized agents of persons accredited specifically by the Administration for this purpose under the regulations contained in this part, or the manufacturer of the gear concerned unless disapproved by the Assistant Secretary.