Collapse to view only § 2887.12 - How do I renew my grant?

§ 2887.10 - When must I amend my application, seek an amendment of my grant or TUP, or obtain a new grant or TUP?

(a) You must amend your application or seek an amendment of your grant or TUP when there is a proposed substantial deviation in location or use.

(b) The requirements to amend an application or a grant or TUP are the same as those for a new application, including paying cost recovery fees and rent according to §§ 2884.12, 2885.23, 2885.19, and 2886.11.

(c) Any activity not authorized by your grant or TUP may subject you to prosecution under applicable law and to trespass charges under subpart 2888 of this part.

(d) Notwithstanding paragraph (a) of this section, if you hold a pipeline grant issued before November 16, 1973, and there is a proposed substantial deviation in location or use of the right-of-way, you must apply for a new grant.

(e) BLM may ratify or confirm a grant that was issued before November 16, 1973, if we can modify the grant to comply with the Act and these regulations. BLM and you must jointly agree to any modification of a grant made under this paragraph.

[70 FR 21078, Apr. 22, 2005, as amended at 89 FR 25976, Apr. 12, 2024]

§ 2887.11 - May I assign or make other changes to my grant or TUP?

(a) With the BLM's approval, you may assign, in whole or in part, any right or interest in a grant or TUP. Assignment actions that may require BLM approval include, but are not limited to, the following:

(1) The transfer by the holder (assignor) of any right or interest in the grant or TUP to a third party (assignee); and

(2) Changes in ownership or other related change in control transactions involving the BLM right-of-way grant holder or TUP holder and another business entity (assignee), including corporate mergers or acquisitions, but not transactions within the same corporate family.

(b) The BLM may require a grant or lease holder to file new or revised information in some circumstances that do not constitute an assignment (see subpart 2883 and §§ 2884.11(c) and 2886.12). Circumstances that would not constitute an assignment but may necessitate this filing include, but are not limited to:

(1) Transactions within the same corporate family;

(2) Changes in the holder's name only (see paragraph (h) of this section); and

(3) Changes in the holder's articles of incorporation.

(c) In order to assign a grant or TUP, the proposed assignee, subject to § 2886.11, must file an application and follow the same procedures and standards as for a new grant or TUP, including paying processing fees (see § 2884.12).

(d) The assignment application must also include:

(1) Documentation that the assignor agrees to the assignment; and

(2) A signed statement that the proposed assignee agrees to comply with and to be bound by the terms and conditions of the grant or TUP that is being assigned and all applicable laws and regulations.

(e) Your assignment is not recognized until the BLM approves it in writing. We will approve the assignment if doing so is in the public interest. The BLM may modify the grant or TUP or add bonding and other requirements, including terms and conditions, to the grant or TUP when approving the assignment. If we approve the assignment, the benefits and liabilities of the grant or TUP apply to the new grant or TUP holder.

(f) The processing time and conditions described at § 2884.21 apply to assignment applications.

(g) Only interests in issued right-of-way grants and TUPs are assignable. Pending right-of-way and TUP applications do not create any property rights or other interest and may not be assigned from one entity to another, except that an entity with a pending application may continue to pursue that application even if that entity becomes a wholly owned subsidiary of a new third party.

(h) Change in name only of holder. Name-only changes are made by individuals, partnerships, corporations, and other right-of-way and TUP holders for a variety of business or legal reasons. To complete a change in name only, (i.e., when the name change in question is not the result of an underlying change in control of the right-of-way grant or TUP), the following requirements must be met:

(1) The holder must file an application requesting a name change and follow the same procedures as for a new grant or TUP, including paying processing fees (see subpart 2884 of this part). The name change request must include:

(i) If the name change is for an individual, a copy of the court order or other legal document effectuating the name change; or

(ii) If the name change is for a corporation, a copy of the corporate resolution(s) proposing and approving the name change, a copy of the filing/acceptance of the change in name by the State or territory in which it is incorporated, and a copy of the appropriate resolution(s), order(s), or other documentation showing the name change.

(2) In connection with processing of a name change only, the BLM retains the authority under § 2885.13(e) to modify the grant or TUP, or add bonding and other requirements, including additional terms and conditions, to the grant or TUP.

(3) Your name change is not recognized until the BLM approves it in writing.

(i) You must seek an amendment of your authorization if you propose a substantial deviation in location or use.

[81 FR 92229, Dec. 19, 2016, as amended at 89 FR 25976, Apr. 12, 2024]

§ 2887.12 - How do I renew my grant?

(a) You must apply to BLM to renew the grant at least 120 calendar days before your grant expires. BLM will renew the grant if the pipeline is being operated and maintained in accordance with the grant, these regulations, and the Act. If your grant has expired or terminated, you must apply for a new grant under subpart 2884 of this part.

(b) The BLM may modify the terms and conditions of the grant at the time of renewal, and you must pay the cost recovery fees.

(c) The time and conditions for processing applications for rights-of-way, as described at § 2884.21 of this part, apply to applications for renewals.

(d) If you make a timely and sufficient application for a renewal of your existing grant or for a new grant in accordance with this section, the existing grant does not expire until we have issued a decision to approve or deny the application.

(e) If we deny your application, you may appeal the decision under § 2881.10.

(f) If you do not submit your application under paragraph (a) of this section at least 120 days prior to authorization expiration, it is considered delinquent; the BLM will not be subject to the customer service standards in this chapter, and it will be processed only as time and resources are available.

(g) The BLM will review your application and determine if you have complied with all of the provisions in this part and whether or not your authorized use will be renewed. The BLM will notify you within 30 days from acceptance of a complete application if it will take longer than 60 days to review your application.

[70 FR 21078, Apr. 22, 2005, as amended at 81 FR 92230, Dec. 19, 2016; 89 FR 25976, Apr. 12, 2024]