§ 126.803 - How will SBA process a HUBZone status protest and what are the possible outcomes?
(a) Date at which eligibility determined. (1) For competitively awarded HUBZone contracts, SBA will determine the eligibility of a concern subject to a HUBZone status protest as of the date of its initial offer that includes price.
(2) For sole source HUBZone contracts, SBA will determine the eligibility of a concern subject to a HUBZone status protest as of the date of the award or intended award.
(3) For protests filed against a HUBZone joint venture alleging that the joint venture does not comply with the requirements in § 126.616, SBA will determine the eligibility of the joint venture as of its final proposal revision for the procurement.
(4) For protests alleging undue reliance on one or more non-HUBZone subcontractors or alleging that such subcontractor(s) will perform the primary and vital requirements of the contract, SBA will determine the HUBZone small business concern's eligibility as of the date of its final proposal revision for the procurement.
(5) For two-step or two-phase procurements, SBA will determine the HUBZone small business concern's eligibility as of the date that it submits its initial bid or proposal (which may or may not include price) during phase one.
(b) Notice of receipt of protest. (1) SBA immediately will notify the contracting officer and the protestor of the date SBA receives a protest and whether SBA will process the protest or dismiss it in accordance with § 126.804.
(2) If SBA determines the protest is timely and sufficiently specific, SBA will notify the protested concern of the protest and the identity of the protestor. The protested concern must submit information responsive to the protest within 5 business days of the date of receipt of the protest.
(c) Burden of proof. In the event of a protest, the burden of proof to demonstrate eligibility is on the protested concern. If a concern does not provide requested information within the allotted time provided by SBA, or if it submits incomplete information, SBA may draw an adverse inference and presume that the information that the concern failed to provide would demonstrate ineligibility and sustain the protest on that basis.
(d) Time period for determination. (1) SBA will determine the HUBZone status of the protested concern within 15 business days after receipt of a complete protest referral.
(2) If SBA does not issue its determination within 15 business days (or request an extension that is granted), the contracting officer may award the contract if he or she determines in writing that there is an immediate need to award the contract and that waiting until SBA makes its determination will be disadvantageous to the Government. Notwithstanding such a determination, the provisions of paragraph (e) of this section apply to the procurement in question.
(e) Notice of determination. SBA will notify the contracting officer, the protestor, and the protested concern of its determination.
(f) Effect of determination. The determination is effective immediately and is final, unless overturned on appeal by SBA's Office of Hearings and Appeals (OHA) pursuant to part 134 of this chapter.
(1) Protest sustained. If the D/HUB finds the protested concern ineligible and sustains the protest, SBA will decertify the concern and remove its designation as a certified HUBZone small business concern in DSBS (or successor system). A contracting officer shall not award a contract to a protested concern that the D/HUB has determined is not an eligible HUBZone small business concern for the procurement in question.
(i) No appeal filed. If a contracting officer receives a determination sustaining a protest after contract award, and no appeal has been filed, the contracting officer shall terminate the award.
(ii) Appeal filed. (A) If a timely appeal is filed after contract award, the contracting officer must consider whether performance can be suspended until an appellate decision is rendered.
(B) If OHA affirms the initial determination finding the protested concern ineligible, the contracting officer shall either terminate the contract or not exercise the next option.
(iii) Update FPDS-NG. Where the contract was awarded to a concern that is found not to qualify as a HUBZone small business concern, the contracting officer must update the Federal Procurement Data System-Next Generation (FPDS-NG) and other procurement reporting databases to reflect the final agency HUBZone decision (i.e., the D/HUB's decision if the protest determination is not appealed, or OHA's decision if the protest determination is appealed).
(2) Protest dismissed or denied. If the D/HUB denies or dismisses the protest, the contracting officer may award the contract to the protested concern.
(i) No appeal filed. If a contracting officer receives a determination dismissing or denying a protest and no appeal has been filed, the contracting officer may:
(A) Award the contract to the protested concern if it has not yet been awarded; or
(B) Authorize contract performance to proceed if the contract has been awarded.
(ii) Appeal filed. If OHA overturns the initial determination or dismissal, the contracting officer may apply the appeal decision to the procurement in question.
(3) A concern found to be ineligible may apply for HUBZone certification immediately after its decline if it believes that it has overcome all reasons for ineligibility through changed circumstances and is currently eligible.