View all text of Subpart E [§ 250.500 - § 250.531]

§ 250.505 - Subsea completions.

No subsea well completion shall be commenced until the lessee obtains written approval from the District Manager in accordance with § 250.513 of this part. That approval shall be based upon a case-by-case determination that the proposed equipment and procedures will adequately control the well and permit safe production operations.