§ 285.614 - When may I begin conducting activities under my approved SAP?

Link to an amendment published at 89 FR 42715, May 15, 2024.

(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.

(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in 30 CFR 585.613(a)(1), you must comply with the requirements of subpart G of this part and submit your safety management system required by § 285.810 before construction may begin.