View all text of Subpart F [§ 585.600 - § 585.703]
§ 585.600 - What plans must I submit to BOEM before I conduct activities on my lease or grant?
You must submit a SAP, COP, or GAP and receive BOEM approval as set forth in the following table:
Before you: | You must submit and obtain approval for your: | (a) Conduct any site assessment activities on your commercial lease | SAP, according to §§ 585.605 through 585.613. | (b) Conduct any activities pertaining to construction of facilities for commercial operations on your commercial lease | COP, according to §§ 585.620 through 585.628. | (c) Conduct any activities on your limited lease, ROW grant, or RUE grant in any OCS area | GAP, according to §§ 585.640 through 585.648. |
---|