- Table 9 to Subpart JJJ of Part 63—Routine Reports Required by This Subpart

Reference Description of report Due date § 63.1335(b) and subpart ARefer to Table 1 and subpart ARefer to subpart A. § 63.1335(e)(3)Precompliance Report aExisting affected sources—December 19, 2000. New affected sources—with application for approval of construction or reconstruction. § 63.1335(e)(4)Emissions Averaging PlanSeptember 19, 2000. § 63.1335(e)(4)(iv)Updates to Emissions Averaging Plan120 days prior to making the change necessitating the update. § 63.1335(e)(5)Notification of Compliance Status bWithin 150 days after the compliance date. § 63.1335(e)(6)Periodic ReportsSemiannually, no later than 60 days after the end of each 6-month period. See § 63.1335(e)(6)(i) for the due date for the first report. § 63.1335(e)(6)(xi)Quarterly reports for Emissions AveragingNo later than 60 days after the end of each quarter. First report is due with the Notification of Compliance Status. § 63.1335(e)(6)(xii)Quarterly reports upon request of the AdministratorNo later than 60 days after the end of each quarter. § 63.1335(e)(7)(i)Storage Vessels Notification of InspectionAt least 30 days prior to the refilling of each storage vessel or the inspection of each storage vessel. § 63.1335(e)(7)(ii)Requests for Approval of a Nominal Control Efficiency for Use in Emissions AveragingInitial submittal is due with the Emissions Averaging Plan specified in § 63.1335(e)(4)(ii); later submittals are made at the discretion of the owner or operator as specified in § 63.1335(e)(7)(ii) (B). § 63.1335(e)(7)(iii)Notification of Change in the Primary Product1. For notification under § 63.1310(f)(3)(ii)—notification submittal date at the discretion of the owner or operator. c2. For notification under § 63.1310(f)(4)(ii)—within 6 months of making the determination.

a There may be two versions of this report due at different times; one for equipment subject to § 63.1331 and one for other emission points subject to this subpart.

b There will be two versions of this report due at different times; one for equipment subject to § 63.1331 and one for other emission points subject to this subpart.

c Note that the TPPU remains subject to this subpart until the notification under § 63.1310(f)(3)(i) is made.

[66 FR 36939, July 16, 2001]