- Table 1 to Subpart BBBB of Part 60—Model Rule—Compliance Schedules and Increments of Progress

Affected units Increment 1 (Submit final control plan) Increment 2 (Award contracts) Increment 3 (Begin onsite construction) Increment 4 (Complete onsite construction) Increment 5 (Final compliance) 1. All Class I units a b(Dates to be specified in State plan)(Dates to be specified in State plan)(Dates to be specified in State plan)(Dates to be specified in State plan)(Dates to be specified in State plan). c d2. All Class II units a e(Dates to be specified in State plan)Not applicableNot applicableNot applicable(Dates to be specified in State plan). c

a Plant specific schedules can be used at the discretion of the State.

b Class I units mean small municipal waste combustion units subject to this subpart that are located at municipal waste combustion plants with an aggregate plant combustion capacity greater than 250 tons per day of municipal solid waste. See § 60.1940 for definitions.

c The date can be no later than 3 years after the effective date of State plan approval or December 6, 2005.

d For Class I units that began construction, reconstruction, or modification after June 26, 1987, comply with the dioxins/furans and mercury limits by the later of two dates:

1. One year after the effective date of State plan approval.

2. One year after the issuance of a revised construction or operation permit, if a permit modification is required.

3. Final compliance with the dioxins/furans limits must be achieved no later than December 6, 2005, even if the date one year after the issuance of a revised construction or operation permit is after December 6, 2005.

e Class II units mean all small municipal combustion units subject to this subpart that are located at municipal waste combustion plants with aggregate plant combustion capacity less than or equal to 250 tons per day of municipal solid waste. See § 60.1940 for definitions.