§ 60.6330 - What are my requirements for meeting increments of progress and achieving final compliance?

If you plan to achieve compliance more than 1 year but less than 3 years following the effective date of state plan approval and a permit modification is not required, or more than 1 year but less than 3 years following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:

(a) Submit a final control plan.

(b) Submit a notification of retrofit contract award.

(c) Initiate onsite construction.

(d) Complete onsite construction.

(e) Achieve final compliance.