- Exhibit A to Subpart A of Part 1924—Estimated Breakdown of Dwelling Costs for Estimating Partial Payments

[In percent]

With slab on grade With crawl space With basement 1. Excavation356 2. Footings, foundations columns8811 3. Floor slab or framing644 4. Subflooring011 5. Wall framing, sheathing776 6. Roof and ceiling framing, sheathing665 7. Roofing554 8. Siding, exterior trim, porches776 9. Windows and exterior doors998 10. Plumbing—roughed in323 11. Sewage disposal111 12. Heating—roughed in111 13. Electrical—roughed in222 14. Insulation222 15. Dry wall or plaster887 16. Basement or porch floor, steps116 17. Heating—finished333 18. Flooring665 19. Interior carpentry, trim, doors665 20. Cabinets and counter tops111 21. Interior painting443 22. Exterior painting111 23. Plumbing—complete fixtures443 24. Electrical—complete fixtures111 25. Finish hardware111 26. Gutters and downspouts111 27. Grading, paving, landscaping333 Total100100100