View all text of Subpart F [§ 3405.16 - § 3405.22]

§ 3405.18 - Use of funds; changes.

(a) Delegation of fiscal responsibility. The grantee may not in whole or in part delegate or transfer to another person, institution, or organization the responsibility for use or expenditure of grant funds.

(b) Change in project plans. (1) The permissible changes by the grantee, project director(s), or other key project personnel in the approved project grant shall be limited to changes in methodology, techniques, or other aspects of the project to expedite achievement of the project's approved goals. If the grantee or the project director(s) are uncertain as to whether a change complies with this provision, the question must be referred to the Department for a final determination.

(2) Changes in approved goals, or objectives, shall be requested by the grantee and approved in writing by the authorized departmental officer prior to effecting such changes. In no event shall requests for such changes be approved that are outside the scope of the approved project.

(3) Changes in approved project leadership or the replacement or reassignment of other key project personnel shall be requested by the grantee and approved in writing by the authorized departmental officer prior to effecting such changes.

(4) Transfers of actual performance of the substantive programmatic work in whole or in part and provisions for payment of funds, whether or not Federal funds are involved, shall be requested by the grantee and approved in writing by the authorized departmental officer prior to effecting such transfers.

(c) Changes in project period. The project period may be extended by the authorized departmental officer without additional financial support for such additional period(s) as the authorized departmental officer determines may be necessary to complete or fulfill the purposes of an approved project. However, due to statutory restriction, no grant may be extended beyond five years from the original start date of the grant, or pre-award date, if applicable. Grant extensions shall be conditioned upon prior request by the grantee and approval in writing by the authorized departmental officer, unless prescribed otherwise in the terms and conditions of a grant.

(d) Changes in approved budget. Changes in an approved budget shall be requested by the grantee and approved in writing by the authorized departmental officer prior to instituting such changes if the revision will:

(1) Involve transfers of amounts budgeted for indirect costs to absorb an increase in direct costs;

(2) Involve transfers of amounts budgeted for direct costs to accommodate changes in indirect cost rates negotiated during a budget period and not approved when a grant was awarded; or

(3) Involve transfers or expenditures of amounts requiring prior approval as set forth in the applicable Federal cost principles, Departmental regulations, or in the grant award.