§ 1b.5 - Environmental assessments.

(a) Generally. If an action is subject to NEPA, as determined following the policy in § 1b.2(e), and unless a USDA subcomponent finds that the proposed action is excluded from having to prepare an environmental assessment or environmental impact statement pursuant to a categorical exclusion as determined following the policy in § 1b.2(f), or by another provision of law, when USDA is the lead agency the USDA subcomponent will prepare an environmental assessment with respect to a proposed action that does not have a reasonably foreseeable significant impact on the quality of the human environment, or if the significance of such effect is unknown. USDA is mindful of Congress' direction that environmental assessments are to be “concise” and set forth the basis of the subcomponent's analysis to support, if appropriate, a finding of no significant impact (NEPA section 106(b)(2); 42 U.S.C. 4336(b)(2).

(b) Scope of analysis. (1) In preparing the environmental assessment, the USDA subcomponent will focus its analysis on whether the environmental effects of the proposed action (and action alternatives, if any) or project at hand are significant.

(2) Similarly, the USDA subcomponent will document in the environmental assessment where and how it drew a reasonable and manageable line relating to its consideration of any environmental effects from the proposed action (and action alternatives, if any) or project at hand that extend outside the geographical territory of the proposal or might materialize later in time.

(3) To the extent it assists in reasoned decision-making, the USDA subcomponent may, but is not required to by NEPA, analyze environmental effects from other actions separate in time, or separate in place, or that fall outside of the USDA subcomponent's regulatory authority, or that would have to be initiated by a third party. If the USDA subcomponent determines that such analysis would assist it in reasoned decision-making, it will document this determination in the environmental assessment and explain where it drew a reasonable and manageable line relating to the consideration of such effects from such separate actions.

(c) Elements. For the purpose of providing evidence and analysis for determining whether to prepare an environmental impact statement or a finding of no significant impact, USDA subcomponents may apply any format they choose for the environmental assessment, but shall address the following elements at a minimum:

(1) Purpose and need for the proposal. The purpose and need should generally be based on the USDA subcomponent's statutory authority. When a subcomponent's statutory duty is to review an application for authorization, the subcomponent may base the purpose and need on the goals of the applicant and the subcomponent's authority.

(2) No action, proposed action, and alternatives (if any). (i) No action may be listed as a stand-alone alternative but is not required. The consequences of taking no action, however, shall be included as part of the environmental impacts analysis to contrast the impacts of the proposed action, and any alternative(s) if developed, with the current condition and expected future condition if the proposed action or alternative were not implemented.

(ii) Alternatives may be included to the extent required by NEPA section 102(2)(H), 42 U.S.C. 4332(2)(H). When there are no unresolved conflicts concerning alternative uses of available resources, the environmental assessment need only analyze the proposed action and may proceed without consideration of additional alternatives.

(iii) Where conflicts have been resolved during development of the proposed action or during the environmental analysis process through iterative modifications to the proposed action—such as addition of design criteria for the proposed action, changing the activities proposed, or adjusting locations of where activities are proposed—this should be described in the environmental assessment as rationale for why additional alternatives were not developed.

(3) Potentially affected environment and environmental impacts. Succinctly describe the potentially affected environment that may be affected by the proposed action and alternatives (if any) under consideration. The environmental assessment may combine the potentially affected environment description with evaluation of the environmental consequences, and it should be no longer than is necessary to provide context for the effects of the proposed action and alternatives (if any). Briefly discuss the reasonably foreseeable environmental impacts of the proposed action and alternatives (if any) and provide sufficient evidence and analysis for determining whether to prepare an environmental impact statement or a finding of no significant impact, taking into consideration the potential for reasonably foreseeable significant impacts as outlined in § 1b.2(f)(3).

(4) Agencies and persons consulted. Provide a succinct list of agencies and persons consulted.

(5) Other environmental reviews. Briefly document determinations for compliance with other applicable laws or regulations, as deemed necessary by the responsible official. When effects analysis is completed to demonstrate compliance with other applicable environmental laws, regulations, or executive orders and already addresses a resource being considered for effects under NEPA (e.g., analysis completed for Endangered Species Act, National Historic Preservation Act, Clean Water Act, etc.) and it is clear from that analysis and compliance discussion that no reasonably foreseeable significant impact exists, the responsible official may rely on that analysis to inform their finding of no significant impact.

(6) Certifying statements for page limit and deadline. The responsible official shall certify the environmental assessment complies with the page limit and deadline required by NEPA. Certification statements shall apply the criteria in paragraphs (d)(4) and (h) of this section.

(d) Page limits—(1) Length of text. The text of an environmental assessment will not exceed 75 pages, not including citations or appendices.

(2) Appendices. Appendices are to be used for voluminous materials, such as scientific tables, collections of data, statistical calculations, and the like, which substantiate the analysis provided in the environmental assessment. Appendices are not to be used to provide additional substantive analysis, because that would circumvent the Congressionally mandated page limits.

(3) Page formatting. Environmental assessments shall be formatted for an 8.5 by 11 inches page with one-inch margins using a word processor with 12-point proportionally spaced font, single spaced. Footnotes may be in 10-point font. Such size restrictions do not apply to explanatory maps, diagrams, graphs, tables, and other means of graphically displaying quantitative or geospatial information, although pages containing such material do count towards the page limit. When an item of graphical material is larger than 8.5 by 11 inches, each such item will count as one page.

(4) Certification related to page limits. The breadth and depth of analysis in an environmental assessment will be tailored to ensure that the environmental analysis does not exceed this page limit. In this regard, as part of the finalization of the environmental assessment, a responsible official will certify (and the certification will be incorporated into the environmental assessment) that the USDA subcomponent has considered the factors mandated by NEPA; that the environmental assessment represents the subcomponent's good-faith effort to prioritize documentation of the substantive issues and most important considerations required by the Act within the congressionally mandated page limits; that this prioritization reflects the subcomponent's expert judgment; and that any issues or considerations addressed briefly or left unaddressed were, in the subcomponent's judgment, comparatively not of a substantive nature (see § 1b.11(53) of this part).

(e) Deadlines. As the Supreme Court has repeatedly held, NEPA is governed by a “rule of reason” and Congress established deadlines for the environmental assessment process in the 2023 revision of NEPA (NEPA section 107(g), 42 U.S.C. 4336a(g)). Thus, USDA subcomponents will complete the environmental assessment not later than the date that is one (1) year after the sooner of, as applicable:

(1) The date on which such agency (or subcomponent) determines that NEPA section 106(b)(2), 42 U.S.C. 4336(b)(2) requires the preparation of an environmental assessment with respect to such action. For internally driven proposals, this determination should not be made until a proposed action is finalized and determined by the responsible official to be ready for interdisciplinary review. For externally-driven proposals (e.g., applications) submitted to a USDA subcomponent which require preparation of an environmental assessment, the responsible official should not make a determination that an action requires the issuance of an environmental assessment until receiving an application the responsible official deems complete and final;

(2) The date on which such agency (or subcomponent) notifies the applicant that the application to establish a right-of-way for such action is complete; or

(3) The date on which such agency (or subcomponent) issues a notice of intent to prepare the environmental assessment for such action. If the subcomponent determines that it will prepare an environmental assessment for a proposed action, the subcomponent may publish notice of intent to publish an environmental assessment. Publication of a notice of intent in the Federal Register for an environmental assessment should be the exception rather than the norm and should only be done for those proposals that are of a more complex scope or scale, such as proposals that are regional or national in scope or other instances for which there are numerous cooperating agencies, or interested or affected parties, given the scope of the actions or scale of the proposal.

(f) Publication of the environmental assessment. USDA subcomponents shall make the environmental assessment available to the public on a USDA website. At the time the environmental assessment is published on the website, it shall be considered complete and conclude the timeline for the environmental assessment. The USDA subcomponent will publish the environmental assessment (unless the deadline is extended pursuant to paragraph (g) of this section), at the latest, on the day the deadline elapses, in as substantially complete form as is possible.

(g) Deadline extensions. The deadlines described in paragraph (e) of this section indicate Congress' determination that an agency has presumptively spent a reasonable amount of time on analysis and the document should issue, absent very unusual circumstances. In such circumstances an extension will be given only for such as time as is necessary to complete the analysis. If a USDA subcomponent determines it is not able to meet the deadline prescribed by NEPA section 107(g)(1)(B), 42 U.S.C. 4336a(g)(1)(B), it must consult with the applicant, if any, pursuant to NEPA section 107(g)(2), 42 U.S.C. 4336a(g)(2). After such consultation, if needed, and for cause stated, it may establish a new deadline. If an extension is approved, the new deadline will be documented in writing and included in the proposal record. The documentation of the new deadline will specify the reason why the environmental assessment was not able to be completed under the statutory deadline and whether the applicant consented to the new deadline. The responsible official should consider if other agencies or persons consulted as part of preparing the environmental assessment need to be notified of the change in the deadline.

(1) Cause for establishing a new deadline is only established if the environmental assessment is so incomplete, at the time at which the USDA subcomponent determines it is not able to meet the statutory deadline, that publication pursuant to paragraph (f) of this section would, in the responsible official's judgment, result in an inadequate analysis that does not meaningfully inform the responsible official's final decision regarding the proposed action or selected alternative (if applicable). Such new deadline must provide only so much additional time as is necessary to complete such environmental assessment.

(2) USDA subcomponents shall coordinate with the USDA Senior Agency Official (Undersecretary of Natural Resources and Environment), or the applicable mission area Under Secretary or other USDA official with delegated authority, prior to extending the deadline for an environmental assessment, in accordance with § 1b.2(b)(5)(iv).

(h) Certification Related to Deadline. When the environmental assessment (EA) is published, the responsible official will certify (and the certification will be incorporated into the environmental assessment) that the resulting EA represents the USDA subcomponent's good-faith effort to fulfill NEPA's requirements within the Congressional timeline; that such effort is substantially complete; that, in the subcomponent's expert opinion, it has thoroughly considered the factors mandated by NEPA; and that, in the responsible official's judgment, the analysis contained therein is adequate to inform and reasonably explain the responsible official's finding regarding the proposed action or selected alternative.