View all text of Subpart C [§ 333.20 - § 333.29]

§ 333.25 - Deadlines.

(a) NEPA is governed by a “rule of reason.” Congress supplied the measure of that reason in the 2023 revision of NEPA by settling the deadlines in NEPA 107(g), 42 U.S.C. 4336a(g). These deadlines indicate Congress's determination that an agency, working with Congress's allocation of resources has presumptively spent a reasonable amount of time on analysis and the document should issue, absent very unusual circumstances. In such circumstances, an extension will be given only for such time as is necessary to complete the analysis. Thus, unless otherwise specified in statute, the District Engineer will complete the environmental impact statement not later than the date that is two years after the date on which the District Engineer determines that the activity requires the issuance of an environmental impact statement.

(b) The end date is either:

(1) When the District Engineer reaches a decision and initially proffers the permit to the applicant or provides the requestor 33 U.S.C. 408 permission; or

(2) When the District Engineer denies the permit or denies permission under 33 U.S.C. 408 with or without prejudice.

(c) The District Engineer will publish the environmental impact statement.

(d) If the District Engineer determines they are not able to meet the deadline prescribed by NEPA section 107(g)(1)(A), 42 U.S.C. 4336a(g)(1)(A), they must consult with the applicant pursuant to NEPA section 107(g)(2), 42 U.S.C. 4336a(g)(2). After such consultation, if needed, and for cause stated, the District Engineer may establish a new deadline and must notify the Division Engineer and Headquarters, U.S. Army Corps of Engineers of the deadline extension. Cause for establishing a new deadline is only established if the environmental impact statement is so incomplete, at the time at which the District Engineer determines they are not able to meet the statutory deadline, that issuance pursuant to paragraph (c) of this section above would, in the District Engineer's view, result in an inadequate analysis. Such new deadline must provide only so much additional time as is necessary to complete such environmental impact statement. The District Engineer will document in the administrative record for the proposed action the new deadline, the reason why the environmental impact statement was not able to be completed under the statutory deadline, when the District Engineer consulted with the applicant on the new deadline, and whether the applicant consented to the new deadline.

(e) When the environmental impact statement is published, the District Engineer will certify (and the certification will be incorporated into the environmental impact statement) that the resulting environmental impact statement represents the Corps' good-faith effort to fulfill NEPA's requirements within the Congressional timeline; that such effort is substantially complete; and that, in the District Engineer's expert opinion, they have thoroughly considered the factors mandated by NEPA; and that, in the District Engineer's judgment, the analysis contained therein is adequate to inform and reasonably explain the District Engineer's decision regarding the proposed Federal activity. .