§ 29.21-5 - Construction.
(a) If construction is not commenced within two (2) years after date of right-of-way grant, the right-of-way may be canceled by the Director of the U.S. Fish and Wildlife Service at his discretion.
(b) Proof of construction: Upon completion of construction, the applicant shall file a certification of completion with the Regional Director.