View all text of Subjgrp 75 [§ 149.600 - § 149.625]

§ 149.610 - What must the District Commander be notified of and when?

The District Commander must be notified of the following:

When— The District Commander must be notified— (a) Construction of a pipeline, platform, or single point mooring (SPM) is plannedAt least 30 days before construction begins. (b) Construction of a pipeline, platform, or SPM beginsWithin 24 hours, from the date construction begins, that the lights and sound signals are in use at the construction site. (c) A light or sound signal is changed during constructionWithin 24 hours of the change. (d) Lights or sound signals used during construction of a platform, buoy, or SPM are replaced by permanent fixtures to meet the requirements of this partWithin 24 hours of replacement. (e) The first cargo transfer operation beginsAt least 60 days before the operation.